3850 N KIM LANE 91436

Certificate Information: 3850 N KIM LANE 91436

Application / Permit
24014-10000-01987
Plan Check / Job No.
B24LA08823
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition (104.31 SF) and remodel to an existing 1-story single family dwelling with an attached garage.
Permit Issued
Issued on 7/2/2024
Issuing Office
Valley
Current Status
Issued on 7/2/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/10/2024 APPLICANT
Assigned to Plan Check Engineer 5/10/2024 NGHI SU
Corrections Issued 5/10/2024 NGHI SU
Plan Check Approved 7/1/2024 DANIEL SMILEY
Issued 7/2/2024 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/14/2024 MICHAEL TEMPLE
Eng Process Fee Ord 176,300 Cleared 5/15/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/15/2024 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 6/28/2024 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,
Engineer Oruncakciel,, Sayat; Lic. No.: C77182 15445 VENTURA BLVD 25      SHERMAN OAKS, CA 91403

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/8/2024 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 7/9/2024 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 7/12/2024 Approved THOMAS FINNILA
Deputy Drilled-In Anchors 7/22/2024 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 8/2/2024 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 8/2/2024 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 8/2/2024 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 8/28/2024 Approved THOMAS FINNILA
ELECTRICAL-Rough 8/28/2024 Approved THOMAS FINNILA
Green Building Rough 8/28/2024 Approved THOMAS FINNILA
Drywall Nailing 9/6/2024 Approved MORRIS JACKSON
Insulation 9/6/2024 Approved MORRIS JACKSON
Interior/Exterior Lathing 9/6/2024 Approved MORRIS JACKSON
Final 2/24/2025 Corrections Issued THOMAS FINNILA
ELECTRICAL-Final 6/18/2025 Approved THOMAS FINNILA
HVAC-Final 6/18/2025 Corrections Issued THOMAS FINNILA
Smoke Detectors 6/18/2025 Approved THOMAS FINNILA
ELECTRICAL-Final 6/26/2025 Approved THOMAS FINNILA
Final 6/26/2025 Conditional Approval THOMAS FINNILA
Green Building Final 6/26/2025 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 6/26/2025 SGSOV Approved THOMAS FINNILA