3633 N MONTALVO ST 90065

Certificate Information: 3633 N MONTALVO ST 90065

Application / Permit
24014-10000-01975
Plan Check / Job No.
B24LA08777
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO (E) SFD "COMPLY WITH DEPARTMENT ORDER effective date 04/01/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 7/31/2024
Issuing Office
Current Status
CofO Issued on 2/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2024 APPLICANT
Assigned to Plan Check Engineer 5/13/2024 KHUONG TRUONG
Corrections Issued 5/14/2024 KHUONG TRUONG
Applicant returned to address corrections 7/10/2024 SHANGQIN XIE
Plan Check Approved 7/23/2024 SUNMIN LEE
Issued 7/31/2024 APPLICANT
CofO in Progress 2/21/2025 FERMIN RUBIO
Permit Finaled 2/27/2025 DANIEL SANCHEZ
CofO Issued 2/27/2025 DANIEL SANCHEZ
Permit Finaled 2/27/2025 DANIEL SANCHEZ

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/28/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/3/2024 WALLIE JONG
Specific Plan Cleared 7/3/2024 PABLO ESTRADA
Grading Pre-Inspection Cleared 7/10/2024 KHUONG TRUONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/6/2024 Approved JACOB SEGURA
ELECTRICAL-Rough 8/13/2024 Corrections Issued JACOB SEGURA
BUILDING-Rough-Frame 9/30/2024 Not Ready for Inspection JACOB SEGURA
ELECTRICAL-Rough 9/30/2024 Not Ready for Inspection JACOB SEGURA
Footing/Foundation/Slab 9/30/2024 Not Ready for Inspection JACOB SEGURA
Green Building Rough 9/30/2024 Not Ready for Inspection JACOB SEGURA
BUILDING-Rough-Frame 10/23/2024 Corrections Issued JACOB SEGURA
Footing/Foundation/Slab 10/23/2024 Corrections Issued JACOB SEGURA
Green Building Rough 10/23/2024 Not Ready for Inspection JACOB SEGURA
ELECTRICAL-Rough 1/24/2025 Partial Approval JACOB SEGURA
Excavation/Setback/Form/Re-Bar 1/24/2025 Partial Approval JACOB SEGURA
Footing/Foundation/Slab 1/24/2025 Partial Approval JACOB SEGURA
BUILDING-Rough-Frame 2/3/2025 Partial Approval JACOB SEGURA
ELECTRICAL-Rough 2/3/2025 Approved JACOB SEGURA
Excavation/Setback/Form/Re-Bar 2/3/2025 Approved JACOB SEGURA
Footing/Foundation/Slab 2/3/2025 Approved JACOB SEGURA
Green Building Rough 2/3/2025 Approved JACOB SEGURA
Drywall Nailing 2/11/2025 Approved JACOB SEGURA
Insulation 2/11/2025 Approved JACOB SEGURA
BUILDING-Rough-Frame 2/19/2025 Approved FERMIN RUBIO
Final 2/19/2025 Not Ready for Inspection FERMIN RUBIO
Green Building Final 2/19/2025 Approved FERMIN RUBIO
Order to Comply 2/19/2025 Not Required FERMIN RUBIO
SGSOV-Seismic Gas S/O Valve 2/19/2025 SGSOV Not Ready FERMIN RUBIO
Smoke Detectors 2/19/2025 Approved FERMIN RUBIO
Final 2/21/2025 OK to Issue CofO FERMIN RUBIO
SGSOV-Seismic Gas S/O Valve 2/21/2025 SGSOV Not Required FERMIN RUBIO