721 N MARTEL AVE 90046
Certificate Information: 721 N MARTEL AVE 90046
- Application / Permit
- 24014-10000-01971
- Plan Check / Job No.
- B24LA08770
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- E-PLAN. ADDITION AND MAJOR REMODEL TO EXISTING 1-STORY SINGLE FAMILY DWELLING R3 OCCUPANCY, TYPE VB CONSTRUCTION, NFPA 13D SPRINKLERED THROUGH OUT
- Permit Issued
- Issued on 6/30/2025
- Issuing Office
- Current Status
- Issued on 6/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | JAD BASMA |
| Corrections Issued | 5/26/2024 | JAD BASMA |
| Quality Review Completed | 6/25/2024 | MICHAEL PEREZ |
| Applicant returned to address corrections | 2/21/2025 | JAD BASMA |
| Plan Check Approved | 4/4/2025 | JAD BASMA |
| No Progress | 4/4/2025 | JAD BASMA |
| Plan Check Approved | 4/4/2025 | JAD BASMA |
| Issued | 6/30/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/18/2024 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 8/6/2024 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/17/2025 | Conditional Approval | JOSH MEISTER |
| METHANE-Barrier | 10/17/2025 | Approved | JOSH MEISTER |
| METHANE-Subgrade | 10/17/2025 | Approved | JOSH MEISTER |
| Underground Mechanical | 10/24/2025 | Approved | JOSH MEISTER |
| Wood Frame | 10/24/2025 | Approved | JOSH MEISTER |
| Insulation | 10/28/2025 | Partial Approval | JOSH MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2025 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2025 | Partial Approval | RONNIE MINDANAO |
| Footing/Foundation/Slab | 11/24/2025 | Approved | RONNIE MINDANAO |
| HVAC-Rough | 11/24/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Rough | 11/24/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Rough-Elec/Plmb/HVAC | 11/24/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2025 | Corrections Issued | JEFFREY MEAD |
| HVAC-Rough | 12/11/2025 | Corrections Issued | JEFFREY MEAD |
| BUILDING-Rough-Frame | 1/9/2026 | Not Ready for Inspection | JOSH MEISTER |
| ELECTRICAL-Rough | 1/9/2026 | Not Ready for Inspection | JOSH MEISTER |
| Green Building Rough | 1/9/2026 | Not Ready for Inspection | JOSH MEISTER |
| HVAC-Rough | 1/9/2026 | Not Ready for Inspection | JOSH MEISTER |
| Interior/Exterior Lathing | 1/9/2026 | Not Ready for Inspection | JOSH MEISTER |
| METHANE-Rough | 1/9/2026 | Not Ready for Inspection | JOSH MEISTER |
| PLUMBING-Rough | 1/9/2026 | Not Ready for Inspection | JOSH MEISTER |
| ELECTRICAL-Rough | 1/12/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 1/12/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/12/2026 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 1/12/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 1/16/2026 | Approved | JOSH MEISTER |
| HVAC-Rough | 1/16/2026 | Approved | JOSH MEISTER |
| PLUMBING-Rough | 1/16/2026 | Approved | JOSH MEISTER |
| Shower Pan | 1/16/2026 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 1/23/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 1/23/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 1/23/2026 | Partial Approval | ENRIQUE MIRELES |
| METHANE-Rough | 1/23/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/27/2026 | Approved | JOSH MEISTER |
| Green Building Rough | 1/27/2026 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 1/27/2026 | Approved | JOSH MEISTER |
| METHANE-Rough | 1/27/2026 | Approved | JOSH MEISTER |
| Sewer | 2/3/2026 | Approved | JOSH MEISTER |
| Insulation | 2/10/2026 | Conditional Approval | JOSH MEISTER |
| Drywall Nailing | 2/20/2026 | Approved | ALEX COLIN |
| Insulation | 2/20/2026 | Approved | ALEX COLIN |