3971 S DALTON AVE 90062
Certificate Information: 3971 S DALTON AVE 90062
- Application / Permit
- 24014-10000-01960
- Plan Check / Job No.
- B24LA08737
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: convert 285 ft detached garage into an ADU & add to it 599 ft
- Permit Issued
- Issued on 5/23/2024
- Issuing Office
- Current Status
- CofO Issued on 11/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2024 | JOSEPH RAFOLS |
| Corrections Issued | 5/14/2024 | JOSEPH RAFOLS |
| Plan Check Approved | 5/22/2024 | JOSEPH RAFOLS |
| Issued | 5/23/2024 | APPLICANT |
| CofO in Progress | 11/19/2024 | SABAS ALONSO |
| Permit Finaled | 11/21/2024 | DEROLD HAUFF |
| Permit Finaled | 11/21/2024 | DEROLD HAUFF |
| CofO Issued | 11/21/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/16/2024 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2024 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 5/21/2024 | CELINA MORENO |
| Sewer availability | Cleared | 5/21/2024 | STEVE MELGAR |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/23/2024 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 7/23/2024 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 7/26/2024 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 7/26/2024 | Not Ready for Inspection | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 7/30/2024 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 7/30/2024 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 7/30/2024 | Partial Approval | SABAS ALONSO |
| Rough-Elec/Plmb/HVAC | 8/20/2024 | Corrections Issued | JOSE MACIAS |
| Wood Frame | 8/20/2024 | Corrections Issued | JOSE MACIAS |
| ELECTRICAL-Rough | 8/23/2024 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 8/23/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 8/23/2024 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/27/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 8/27/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2024 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 8/27/2024 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 8/27/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 8/27/2024 | Approved | SABAS ALONSO |
| Deputy Wood Construction | 8/28/2024 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2024 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 8/28/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/30/2024 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 8/30/2024 | Not Ready for Inspection | SABAS ALONSO |
| Rough-Elec/Plmb/HVAC | 8/30/2024 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/4/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 9/4/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/4/2024 | Partial Approval | SABAS ALONSO |
| Insulation | 9/6/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 9/10/2024 | Not Ready for Inspection | LUIS CASTRO |
| Drywall Nailing | 9/11/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/11/2024 | Not Ready for Inspection | SABAS ALONSO |
| Shower Pan | 9/11/2024 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 9/20/2024 | Approved | SABAS ALONSO |
| Shower Pan | 9/20/2024 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 9/24/2024 | Approved | ALEX COLIN |
| Final | 10/28/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 10/28/2024 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 10/28/2024 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 10/28/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 10/30/2024 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 10/30/2024 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 10/30/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 11/6/2024 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 11/6/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/6/2024 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 11/6/2024 | Approved | SABAS ALONSO |
| Final | 11/13/2024 | Corrections Issued | SABAS ALONSO |
| Final | 11/18/2024 | OK to Issue CofO | SABAS ALONSO |