16736 W TRIBUNE ST 91344

Certificate Information: 16736 W TRIBUNE ST 91344

Application / Permit
24014-10000-01930
Plan Check / Job No.
B24LA08615
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERSION OF THE (E) DETACHED GARAGE TO 23'-5" X 54'-6" ACCESSORY DWELLING UNIT ALL WORK PER WFPP (1,200 SF max per Ordinance, LAMC 12.22 A.33(c)-(d))
Permit Issued
Issued on 5/29/2024
Issuing Office
Metro
Current Status
CofO Issued on 12/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 AUNG SOE
Corrections Issued 5/14/2024 AUNG SOE
Applicant returned to address corrections 5/29/2024 ALEXANDER JOO
Plan Check Approved 5/29/2024 ALEXANDER JOO
Issued 5/29/2024 APPLICANT
CofO in Progress 11/13/2024 JAVIER RAMOS JR
Permit Finaled 12/16/2024 RUBEN SALAS
CofO Issued 12/16/2024 RUBEN SALAS
Permit Finaled 12/16/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/20/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/20/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/21/2024 BIAINA HARITUNIAN
Sewer availability Cleared 5/21/2024 BIAINA HARITUNIAN

Contact Information

Contractor Creative Touch Construction Corp; Lic. No.: 1007576-B 22854 LULL STREET      WEST HILLS, CA 91304

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/15/2024 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 7/18/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 7/18/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 8/6/2024 Approved JAVIER RAMOS JR
Sewer 8/6/2024 Approved JAVIER RAMOS JR
Underground Mechanical 8/6/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 8/27/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 8/27/2024 Approved CHRISTOPHER ROJAS
Final 8/27/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 8/27/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 8/27/2024 Approved CHRISTOPHER ROJAS
Insulation 9/6/2024 Approved SALVADOR MARTINEZ
Drywall Nailing 9/11/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 9/11/2024 Approved LOUIS ESCOTO
Shower Pan 10/3/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 10/9/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 11/4/2024 Partial Inspection JAVIER RAMOS JR
Final 11/4/2024 Corrections Issued JAVIER RAMOS JR
Green Building Final 11/4/2024 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 11/4/2024 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 11/4/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 11/12/2024 Approved JAVIER RAMOS JR
Final 11/12/2024 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 11/12/2024 Approved JAVIER RAMOS JR
HVAC-Final 11/12/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 11/12/2024 Approved JAVIER RAMOS JR
Service/Power Release 11/12/2024 Approved JAVIER RAMOS JR