11917 W ANETA ST 90230
Certificate Information: 11917 W ANETA ST 90230
- Application / Permit
- 24014-10000-01923
- Plan Check / Job No.
- B24LA08595
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* 1ST AND SECOND STORY ADDITION AND REMODEL TO EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 12/3/2024
- Issuing Office
- Current Status
- CofO Issued on 3/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2024 | SELLA BENYAMIN |
| Corrections Issued | 5/21/2024 | SELLA BENYAMIN |
| Quality Review Completed | 5/30/2024 | STEVEN KIM |
| Applicant returned to address corrections | 8/30/2024 | SELLA BENYAMIN |
| Plan Check Approved | 10/18/2024 | SELLA BENYAMIN |
| Issued | 12/3/2024 | APPLICANT |
| CofO in Progress | 2/23/2026 | ANTHONY EGSON |
| Permit Finaled | 3/3/2026 | RICHARD STEINBACH |
| CofO Issued | 3/3/2026 | RICHARD STEINBACH |
| Permit Finaled | 3/3/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/25/2024 | KIMBERLY HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/5/2024 | KIMBERLY HERNANDEZ |
| Sewer availability | Cleared | 7/5/2024 | KIMBERLY HERNANDEZ |
Contact Information
| Contractor | Nittay Inc; Lic. No.: 1033506-B | , |
| Contractor | P M A Renovations; Lic. No.: 1033506-B | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 1/28/2025 | Approved | BOBBY KEY |
| PLUMBING-Rough | 1/28/2025 | Partial Approval | BOBBY KEY |
| Deputy Drilled-In Anchors | 2/4/2025 | Partial Approval | MICHAEL ALLEN |
| Footing/Foundation/Slab | 2/11/2025 | Approved | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2025 | Partial Approval | MICHAEL ALLEN |
| Deputy Wood Construction | 2/26/2025 | Partial Approval | MICHAEL ALLEN |
| Deputy Wood Construction | 3/20/2025 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Corrections Issued | RUBEN RIVAS |
| Special/Order Compliance | 3/21/2025 | Partial Inspection | STEPHANIE SWANSON |
| Special/Order Compliance | 3/26/2025 | Partial Inspection | BOBBY KEY |
| Wood Frame | 3/26/2025 | Corrections Issued | RUBEN RIVAS |
| BUILDING-Rough-Frame | 4/4/2025 | Partial Approval | RUBEN RIVAS |
| Deputy Wood Construction | 4/4/2025 | Partial Approval | RUBEN RIVAS |
| Green Building Rough | 4/4/2025 | Not Ready for Inspection | RUBEN RIVAS |
| MERV13>=Rough | 4/4/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Footing/Foundation/Slab | 4/15/2025 | Corrections Issued | RUBEN RIVAS |
| HVAC-Rough | 4/15/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 4/15/2025 | Corrections Issued | RUBEN RIVAS |
| Shower Pan | 4/15/2025 | Approved | RUBEN RIVAS |
| ELECTRICAL-Rough | 4/21/2025 | Partial Approval | RUBEN RIVAS |
| Interior/Exterior Lathing | 4/21/2025 | Partial Approval | RUBEN RIVAS |
| PLUMBING-Rough | 4/21/2025 | Partial Approval | RUBEN RIVAS |
| BUILDING-Rough-Frame | 4/22/2025 | Corrections Issued | RUBEN RIVAS |
| Green Building Rough | 4/22/2025 | Not Ready for Inspection | RUBEN RIVAS |
| MERV13>=Rough | 4/22/2025 | Not Ready for Inspection | RUBEN RIVAS |
| BUILDING-Rough-Frame | 4/29/2025 | Partial Approval | RUBEN RIVAS |
| Green Building Rough | 4/29/2025 | Approved | RUBEN RIVAS |
| MERV13>=Rough | 4/29/2025 | Approved | RUBEN RIVAS |
| Insulation | 5/9/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 5/9/2025 | Partial Approval | RUBEN RIVAS |
| Drywall Nailing | 5/15/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 11/13/2025 | Approved | RUBEN RIVAS |
| Final | 11/13/2025 | Corrections Issued | RUBEN RIVAS |
| Footing/Foundation/Slab | 11/13/2025 | Approved | RUBEN RIVAS |
| Green Building Final | 11/13/2025 | Approved | RUBEN RIVAS |
| MERV13>=Final | 11/13/2025 | Corrections Issued | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 11/13/2025 | SGSOV Approved | RUBEN RIVAS |
| Smoke Detectors | 11/13/2025 | Approved | RUBEN RIVAS |
| ELECTRICAL-Final | 11/21/2025 | Approved | WILBER ROSALES |
| Final | 11/21/2025 | Corrections Issued | WILBER ROSALES |
| HVAC-Final | 11/21/2025 | Corrections Issued | WILBER ROSALES |
| MERV13>=Final | 11/21/2025 | Not Ready for Inspection | WILBER ROSALES |
| PLUMBING-Final | 11/21/2025 | Approved | WILBER ROSALES |
| Final | 12/1/2025 | Corrections Issued | ANTHONY EGSON |
| MERV13>=Final | 12/1/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 1/20/2026 | Not Ready for Inspection | ANTHONY EGSON |
| MERV13>=Final | 1/20/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 2/12/2026 | Not Ready for Inspection | ANTHONY EGSON |
| MERV13>=Final | 2/12/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 2/20/2026 | OK to Issue CofO | ANTHONY EGSON |
| HVAC-Final | 2/20/2026 | Approved | ANTHONY EGSON |
| MERV13>=Final | 2/20/2026 | Approved | ANTHONY EGSON |
| Service/Power Release | 2/26/2026 | Approved | DAVID FEILER |