4721 S CAMPBELL DR 90230
Certificate Information: 4721 S CAMPBELL DR 90230
- Application / Permit
- 24014-10000-01909
- Plan Check / Job No.
- B24LA08538
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and addition to (e) 1-story SFD, NFPA 13D sprinklered throughout.
- Permit Issued
- Issued on 11/8/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2024 | KELVIN CHUONG |
| Corrections Issued | 5/13/2024 | KELVIN CHUONG |
| Building Plans Picked Up | 5/14/2024 | APPLICANT |
| Plan Check Approved | 6/18/2024 | CRISTINA SALAZAR |
| Issued | 11/8/2024 | APPLICANT |
| CofO in Progress | 8/29/2025 | WILBER ROSALES |
| Permit Finaled | 10/2/2025 | RICHARD STEINBACH |
| CofO Issued | 10/2/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/2/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/17/2024 | BRENDEN HAWK |
| Sewer availability | Cleared | 5/17/2024 | BRENDEN HAWK |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2024 | BRENDEN HAWK |
| Roof/Waste drainage to street | Cleared | 6/16/2024 | BRENDEN HAWK |
Contact Information
| Contractor | Ap Remodeling Inc; Lic. No.: 1049032-B | 5555 INGLEWOOD BLVD #202 CULVER CITY, CA 90230 |
| Engineer | Chung,, Jun Sung; Lic. No.: S2766 | 15909 CARMENIA DR WHITTIER, CA 90603 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/4/2024 | Conditional Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 12/5/2024 | Not Ready for Inspection | JESUS PINEDA |
| Footing/Foundation/Slab | 12/5/2024 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 12/11/2024 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 12/12/2024 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 12/12/2024 | Partial Inspection | JAYLIN GRAVITTE |
| Footing/Foundation/Slab | 12/16/2024 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2025 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 1/8/2025 | Corrections Issued | MICHAEL ALLEN |
| Footing/Foundation/Slab | 1/10/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 1/10/2025 | Partial Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2025 | Partial Approval | JESUS PINEDA |
| Insulation | 1/15/2025 | Partial Approval | JESUS PINEDA |
| Deputy Wood Construction | 2/4/2025 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Conditional Approval | MICHAEL ALLEN |
| Green Building Rough | 2/4/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Verify Sprinkler Sign Off | 2/4/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Interior/Exterior Lathing | 2/20/2025 | Partial Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 3/3/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Rough | 3/3/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 3/3/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 3/3/2025 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 3/6/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Rough | 3/6/2025 | Approved | JESUS PINEDA |
| Rough-Elec/Plmb/HVAC | 3/6/2025 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 3/6/2025 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 3/12/2025 | Not Ready for Inspection | BOBBY KEY |
| Insulation | 3/12/2025 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 3/12/2025 | Not Ready for Inspection | BOBBY KEY |
| Shower Pan | 3/12/2025 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 3/13/2025 | Approved | BOBBY KEY |
| Insulation | 3/13/2025 | Approved | BOBBY KEY |
| Drywall Nailing | 3/17/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 3/17/2025 | Approved | RUBEN RIVAS |
| Special/Order Compliance | 3/17/2025 | Partial Inspection | BOBBY KEY |
| ELECTRICAL-Final | 5/21/2025 | Corrections Issued | RUBEN RIVAS |
| Final | 5/21/2025 | Corrections Issued | RUBEN RIVAS |
| Green Building Final | 5/21/2025 | Approved | RUBEN RIVAS |
| HVAC-Final | 5/21/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 5/21/2025 | Corrections Issued | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 5/21/2025 | SGSOV Approved | RUBEN RIVAS |
| Smoke Detectors | 5/21/2025 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Final | 6/24/2025 | Approved | MICHAEL ALLEN |
| Final | 6/24/2025 | Corrections Issued | MICHAEL ALLEN |
| HVAC-Final | 6/24/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 6/24/2025 | Approved | MICHAEL ALLEN |
| Smoke Detectors | 6/24/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 8/27/2025 | Approved | WILBER ROSALES |
| Final | 8/27/2025 | OK to Issue CofO | WILBER ROSALES |
| HVAC-Final | 8/27/2025 | Approved | WILBER ROSALES |
| PLUMBING-Final | 8/27/2025 | Approved | WILBER ROSALES |