509 N NEVA PL 90042
Certificate Information: 509 N NEVA PL 90042
- Application / Permit
- 24014-10000-01904
- Plan Check / Job No.
- B24LA08530
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE WITH UNPERMITTED PORTION TO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). "COMPLY WITH DEPARTMENT ORDER effective date 03/26/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". Existing construction that does not pose a threat to the publics health and safety was allowed per Government Code Section 55.852.2(d)(2).
- Permit Issued
- Issued on 7/10/2025
- Issuing Office
- Current Status
- Issued on 7/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/10/2024 | MADISON ODELL |
| Corrections Issued | 5/11/2024 | MADISON ODELL |
| Applicant returned to address corrections | 7/11/2024 | MADISON ODELL |
| Applicant returned to address corrections | 8/28/2024 | MADISON ODELL |
| Applicant returned to address corrections | 10/18/2024 | MADISON ODELL |
| Applicant returned to address corrections | 11/6/2024 | MADISON ODELL |
| Plan Check Approved | 11/20/2024 | MADISON O'DELL |
| Issued | 7/10/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/21/2024 | MICHAEL TEMPLE |
| Address approval | Cleared | 6/24/2024 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 6/24/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2024 | WALLIE JONG |
| Sewer availability | Cleared | 6/25/2024 | WALLIE JONG |
Contact Information
| Architect | Buangsuwon,, Panupong; Lic. No.: NA18986 | , |
| Contractor | Kelly Construction; Lic. No.: 749070-B | 2100 LORAIN ROAD SAN MARINO, CA 91108 |
Inspector Information
| DANIEL DELACRUZ, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO SIERRA, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT MINASSIANS, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/25/2025 | Approved | DANIEL DELACRUZ |
| Footing/Foundation/Slab | 1/23/2026 | Not Ready for Inspection | DANIEL DELACRUZ |
| Footing/Foundation/Slab | 1/28/2026 | Partial Approval | DANIEL DELACRUZ |
| Footing/Foundation/Slab | 3/4/2026 | Partial Approval | DANIEL DELACRUZ |
| Footing/Foundation/Slab | 3/10/2026 | Approved | DANIEL DELACRUZ |
| PLUMBING-Rough | 3/10/2026 | Not Ready for Inspection | DANIEL DELACRUZ |
| BUILDING-Rough-Frame | 3/16/2026 | Corrections Issued | ROBERT MINASSIANS |
| PLUMBING-Rough | 3/16/2026 | Conditional Approval | ROBERT MINASSIANS |
| BUILDING-Rough-Frame | 4/15/2026 | Partial Approval | DANIEL DELACRUZ |
| ELECTRICAL-Rough | 4/15/2026 | Approved | DANIEL DELACRUZ |
| Green Building Rough | 4/15/2026 | Approved | DANIEL DELACRUZ |
| HVAC-Rough | 4/15/2026 | Approved | DANIEL DELACRUZ |
| PLUMBING-Rough | 4/15/2026 | Approved | DANIEL DELACRUZ |
| Insulation | 4/21/2026 | Approved | DANIEL DELACRUZ |
| BUILDING-Rough-Frame | 4/28/2026 | Approved | DANIEL DELACRUZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2026 | Not Ready for Inspection | DANIEL DELACRUZ |
| Shower Pan | 4/28/2026 | Not Ready for Inspection | DANIEL DELACRUZ |
| Deputy Wood Construction | 5/1/2026 | No Result Entered | JAVIER LANDEROS |
| Drywall Nailing | 5/5/2026 | Approved | DANIEL DELACRUZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2026 | Approved | DANIEL DELACRUZ |
| Shower Pan | 5/5/2026 | Approved | DANIEL DELACRUZ |
| Interior/Exterior Lathing | 5/14/2026 | Approved | DANIEL DELACRUZ |
| Interior/Exterior Lathing | 5/20/2026 | Approved | DANIEL DELACRUZ |