17227 W BULLOCK ST 91316

Certificate Information: 17227 W BULLOCK ST 91316

Application / Permit
24014-10000-01901
Plan Check / Job No.
B24LA08497
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-story addition to (E) sfd.
Permit Issued
Issued on 1/30/2025
Issuing Office
Current Status
CofO Issued on 4/25/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/28/2024 APPLICANT
Assigned to Plan Check Engineer 6/3/2024 SERGIO MUNIZ
Corrections Issued 6/4/2024 SERGIO MUNIZ
Applicant returned to address corrections 11/15/2024 SERGIO MUNIZ
Applicant returned to address corrections 11/20/2024 SERGIO MUNIZ
Applicant returned to address corrections 1/14/2025 SERGIO MUNIZ
Plan Check Approved 1/18/2025 SERGIO MUNIZ
Issued 1/30/2025 APPLICANT
CofO in Progress 12/3/2025 MORRIS JACKSON
Permit Finaled 4/25/2026 MICHAEL PELHAM
CofO Issued 4/25/2026 MICHAEL PELHAM
Permit Finaled 4/25/2026 MICHAEL PELHAM

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/10/2024 BIAINA HARITUNIAN
Sewer availability Cleared 9/4/2024 ROSE MARIE SMITH
Eng Process Fee Ord 176,300 Cleared 10/1/2024 BIAINA HARITUNIAN

Contact Information

Contractor M R D Construction; Lic. No.: 960463-B 13719 VENTURA BLVD UNIT D      SHERMAN OAKS, CA 91423

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/28/2025 Conditional Approval JON MCHUGH
Footing/Foundation/Slab 4/11/2025 Approved MORRIS JACKSON
Deputy Drilled-In Anchors 4/25/2025 Conditional Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 4/29/2025 Partial Approval MORRIS JACKSON
PLUMBING-Rough 4/29/2025 Partial Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 5/1/2025 Partial Approval MORRIS JACKSON
Insulation 5/1/2025 Partial Approval MORRIS JACKSON
ELECTRICAL-Rough 5/15/2025 Corrections Issued MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 5/15/2025 Not Ready for Inspection MORRIS JACKSON
PLUMBING-Rough 5/15/2025 Approved MORRIS JACKSON
ELECTRICAL-Rough 5/22/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 5/22/2025 Not Ready for Inspection MORRIS JACKSON
HVAC-Rough 5/22/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 5/27/2025 Partial Approval MORRIS JACKSON
BUILDING-Rough-Frame 6/3/2025 Approved MORRIS JACKSON
Green Building Rough 6/3/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 6/3/2025 Partial Approval MORRIS JACKSON
MERV13>=Rough 6/3/2025 Approved MORRIS JACKSON
Insulation 6/9/2025 Approved MORRIS JACKSON
Drywall Nailing 6/18/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 6/18/2025 Approved MORRIS JACKSON
Final 8/21/2025 Corrections Issued MORRIS JACKSON
Green Building Final 8/21/2025 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 8/21/2025 SGSOV Approved MORRIS JACKSON
Smoke Detectors 8/21/2025 Approved MORRIS JACKSON
Final 11/25/2025 OK to Issue CofO MORRIS JACKSON