(1) Dwelling - Single Family
Work Description
**ePlan** Addition to existing SFD
Permit Issued
Issued on 6/4/2024
Issuing Office
Current Status
CofO Issued on 1/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2024 APPLICANT
Assigned to Plan Check Engineer 5/10/2024 JOHNPAUL ISIP
Corrections Issued 5/14/2024 JOHNPAUL ISIP
Plan Check Approved 6/2/2024 EDWIN ESPIN
Issued 6/4/2024 APPLICANT
CofO in Progress 11/6/2024 JENNIFER RABUCHIN
Permit Finaled 1/24/2025 RUBEN SALAS
CofO Issued 1/24/2025 RUBEN SALAS
Permit Finaled 1/24/2025 RUBEN SALAS

Permit Application Clearance Information

ZI Cleared 5/20/2024 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 5/23/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/23/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/8/2024 Conditional Approval MISAEL ESPARZA
Footing/Foundation/Slab 7/8/2024 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 7/10/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 7/18/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 7/18/2024 Conditional Approval MISAEL ESPARZA
BUILDING-Rough-Frame 7/23/2024 Partial Approval VINCENT HANLEY
PLUMBING-Rough 7/23/2024 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 7/24/2024 Not Ready for Inspection MICHAEL CORTEZ
Insulation 7/24/2024 Approved MICHAEL CORTEZ
Floor/Roof Diaphrgm/Shear Wall 7/26/2024 Partial Approval JACK KARGODORIAN
Deputy Wood Construction 8/19/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 8/20/2024 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 8/20/2024 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 8/20/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 8/23/2024 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 8/23/2024 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 9/11/2024 Partial Approval MISAEL ESPARZA
ELECTRICAL-Rough 9/16/2024 Corrections Issued MISAEL ESPARZA
HVAC-Rough 9/16/2024 Approved MISAEL ESPARZA
PLUMBING-Rough 9/16/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 9/17/2024 Approved MISAEL ESPARZA
ELECTRICAL-Rough 9/17/2024 Approved MISAEL ESPARZA
Green Building Rough 9/17/2024 Approved MISAEL ESPARZA
Wood Frame 9/17/2024 Approved MISAEL ESPARZA
Gas Test 9/19/2024 Partial Approval MISAEL ESPARZA
Insulation 9/19/2024 Approved MISAEL ESPARZA
Drywall Nailing 9/23/2024 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 9/26/2024 Approved MISAEL ESPARZA
ELECTRICAL-Final 11/1/2024 Corrections Issued JENNIFER RABUCHIN
Final 11/1/2024 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 11/1/2024 Approved JENNIFER RABUCHIN
HVAC-Final 11/1/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 11/1/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/1/2024 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 11/1/2024 Approved JENNIFER RABUCHIN