3402 S GRAND VIEW BLVD 90066

Certificate Information: 3402 S GRAND VIEW BLVD 90066

Application / Permit
24014-10000-01878
Plan Check / Job No.
B24LA08406
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE (360 SF), STORAGE (144 SF) TO (N) ADU WITH ADDITION PER ENGINEER DESIGN (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 11/8/2024
Issuing Office
Current Status
CofO Issued on 8/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 AUNG SOE
Corrections Issued 5/14/2024 AUNG SOE
Building Plans Picked Up 5/30/2024 APPLICANT
Plan Check Approved 11/4/2024 JOHN MESIAS
Issued 11/8/2024 APPLICANT
CofO in Progress 8/1/2025 MICHAEL ALLEN
Permit Finaled 8/4/2025 RICHARD STEINBACH
CofO Issued 8/4/2025 RICHARD STEINBACH
Permit Finaled 8/4/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/30/2024 VLADIMIR ARUTYUNYAN
Specific Plan Cleared 6/21/2024 PEDRO AYALA
Construction near power lines Cleared 10/23/2024 TINA MIRANDA
Construction within easement Cleared 10/23/2024 TINA MIRANDA
Eng Process Fee Ord 176,300 Cleared 10/31/2024 DARIN LAM
Roof/Waste drainage to street Cleared 10/31/2024 DARIN LAM
Sewer availability Cleared 10/31/2024 DARIN LAM
Grading Pre-Inspection Cleared 11/5/2024 LANNY MERRICK

Contact Information

Contractor My Home Builders Inc; Lic. No.: 1002927-B 20720 VENTURA BLVD 280      WOODLAND HILLS, CA 91364
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/11/2025 Conditional Approval DANIEL VERA
Footing/Foundation/Slab 2/12/2025 Approved DANIEL VERA
Underground Mechanical 2/12/2025 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 2/21/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 3/21/2025 Corrections Issued WILBER ROSALES
Gas Test 3/21/2025 Approved WILBER ROSALES
Green Building Rough 3/21/2025 Not Ready for Inspection WILBER ROSALES
Rough-Elec/Plmb/HVAC 3/21/2025 Corrections Issued WILBER ROSALES
Special/Order Compliance 3/21/2025 Partial Inspection TEMISTOCLES CAAL
BUILDING-Rough-Frame 4/1/2025 Approved WILBER ROSALES
ELECTRICAL-Rough 4/1/2025 Approved WILBER ROSALES
Green Building Rough 4/1/2025 Approved WILBER ROSALES
HVAC-Rough 4/1/2025 Approved WILBER ROSALES
PLUMBING-Rough 4/1/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 4/4/2025 Approved WILBER ROSALES
Insulation 4/10/2025 Approved WILBER ROSALES
Interior/Exterior Lathing 4/10/2025 Approved WILBER ROSALES
Shower Pan 4/10/2025 Approved WILBER ROSALES
Drywall Nailing 4/30/2025 Approved WILBER ROSALES
Gas Test 6/5/2025 Approved WILBER ROSALES
Sewer 6/5/2025 Approved WILBER ROSALES
ELECTRICAL-Final 7/28/2025 Corrections Issued MICHAEL ALLEN
Final 7/28/2025 Corrections Issued MICHAEL ALLEN
Green Building Final 7/28/2025 Approved MICHAEL ALLEN
Green Building Rough 7/28/2025 Approved MICHAEL ALLEN
HVAC-Final 7/28/2025 Corrections Issued MICHAEL ALLEN
PLUMBING-Final 7/28/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 7/28/2025 SGSOV Not Ready MICHAEL ALLEN
Smoke Detectors 7/28/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 7/31/2025 Approved MICHAEL ALLEN
Final 7/31/2025 OK to Issue CofO MICHAEL ALLEN
HVAC-Final 7/31/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 7/31/2025 SGSOV Approved MICHAEL ALLEN