12842 W RUBENS AVE 90066

Certificate Information: 12842 W RUBENS AVE 90066

Application / Permit
24014-10000-01868
Plan Check / Job No.
B24LA08377
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE WITH ADDITION TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 7/26/2024
Issuing Office
Current Status
CofO Issued on 7/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 ALEC MOUSAKHANIAN
Corrections Issued 5/10/2024 ALEC MOUSAKHANIAN
Plan Check Approved 7/10/2024 ALEC MOUSAKHANIAN
Issued 7/26/2024 APPLICANT
CofO in Progress 7/16/2025 RUBEN RIVAS
Permit Finaled 7/21/2025 RICHARD STEINBACH
CofO Issued 7/21/2025 RICHARD STEINBACH
Permit Finaled 7/21/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/15/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/15/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/17/2024 CARLOS AGUILERA
Sewer availability Cleared 6/17/2024 CARLOS AGUILERA
Specific Plan Cleared 6/20/2024 JOSHUA JONES

Contact Information

Contractor Owner-Builder       ,
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/22/2024 Corrections Issued MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 1/16/2025 Approved MICHAEL ALLEN
Footing/Foundation/Slab 1/16/2025 Approved MICHAEL ALLEN
METHANE-Barrier 1/16/2025 Not Ready for Inspection MICHAEL ALLEN
METHANE-Subgrade 1/16/2025 Not Ready for Inspection MICHAEL ALLEN
PLUMBING-Rough 1/16/2025 Partial Approval MICHAEL ALLEN
BUILDING-Rough-Frame 4/1/2025 Not Ready for Inspection RUBEN RIVAS
ELECTRICAL-Rough 4/1/2025 Approved RUBEN RIVAS
Green Building Rough 4/1/2025 Not Ready for Inspection RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 4/3/2025 Partial Approval ARAM AVEDISIAN
Insulation 4/9/2025 Partial Approval RUBEN RIVAS
Insulation 4/21/2025 Not Ready for Inspection RUBEN RIVAS
Interior/Exterior Lathing 4/21/2025 Not Ready for Inspection RUBEN RIVAS
BUILDING-Rough-Frame 4/28/2025 Approved JESUS RODRIGUEZ
Green Building Rough 4/28/2025 Approved JESUS RODRIGUEZ
HVAC-Rough 4/28/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 4/28/2025 Approved JESUS RODRIGUEZ
PLUMBING-Rough 4/28/2025 Approved JESUS RODRIGUEZ
Drywall Nailing 5/6/2025 Approved RUBEN RIVAS
Interior/Exterior Lathing 5/7/2025 Approved RUBEN RIVAS
ELECTRICAL-Final 6/25/2025 Not Ready for Inspection RUBEN RIVAS
Final 6/25/2025 Not Ready for Inspection RUBEN RIVAS
Green Building Final 6/25/2025 Approved RUBEN RIVAS
HVAC-Final 6/25/2025 Not Ready for Inspection RUBEN RIVAS
PLUMBING-Final 6/25/2025 Corrections Issued RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 6/25/2025 SGSOV Not Ready RUBEN RIVAS
Smoke Detectors 6/25/2025 Approved RUBEN RIVAS
PLUMBING-Final 7/1/2025 Approved RUBEN RIVAS
ELECTRICAL-Final 7/15/2025 Approved RUBEN RIVAS
Final 7/15/2025 OK to Issue CofO RUBEN RIVAS
SGSOV-Seismic Gas S/O Valve 7/15/2025 SGSOV Approved RUBEN RIVAS