1538 N OGDEN DR 90046
Certificate Information: 1538 N OGDEN DR 90046
- Application / Permit
- 24014-10000-01858
- Plan Check / Job No.
- B24LA08346
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan ADDITION AND REMODEL TO (E) 2-STORY SFD, WITH NEW ATTACHED TRELLIS.
- Permit Issued
- Issued on 6/20/2025
- Issuing Office
- Current Status
- Issued on 6/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2024 | ADRIANA LOPEZ |
| Corrections Issued | 5/28/2024 | ADRIANA LOPEZ |
| Quality Review Completed | 6/18/2024 | SINA KHOSRAVI |
| Applicant returned to address corrections | 5/1/2025 | ADRIANA LOPEZ |
| Plan Check Approved | 6/9/2025 | ADRIANA LOPEZ |
| No Progress | 6/12/2025 | ADRIANA LOPEZ |
| Plan Check Approved | 6/12/2025 | ADRIANA LOPEZ |
| Issued | 6/20/2025 | APPLICANT |
Permit Application Clearance Information
| HPOZ | Cleared | 11/1/2024 | JORGE RUIZ |
| Specific Plan | Cleared | 11/1/2024 | JORGE RUIZ |
| Roof/Waste drainage to street | Cleared | 11/8/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2024 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/8/2025 | Approved | ROY SPAULDING |
| Footing/Foundation/Slab | 7/22/2025 | Corrections Issued | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 7/23/2025 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 10/31/2025 | Corrections Issued | ROY SPAULDING |
| ELECTRICAL-Rough | 10/31/2025 | Not Ready for Inspection | ROY SPAULDING |
| Green Building Rough | 10/31/2025 | Not Ready for Inspection | ROY SPAULDING |
| HVAC-Rough | 10/31/2025 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Rough | 10/31/2025 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 11/3/2025 | Corrections Issued | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2025 | Approved | ROY SPAULDING |
| HVAC-Rough | 11/3/2025 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 11/3/2025 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 11/5/2025 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 11/5/2025 | Approved | ROY SPAULDING |
| Green Building Rough | 11/5/2025 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 11/13/2025 | Approved | ROY SPAULDING |
| Insulation | 11/18/2025 | Approved | DAVID WILLIAMS |
| Special/Order Compliance | 11/18/2025 | Corrections Issued | DAVID WILLIAMS |
| Drywall Nailing | 12/4/2025 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 12/4/2025 | Approved | ROY SPAULDING |