3488 S 2ND AVE 90018

Certificate Information: 3488 S 2ND AVE 90018

Application / Permit
24014-10000-01853
Plan Check / Job No.
B24LA08331
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVAL OF EXISTING 27'-0" X 6'-5 1/2" LIVABLE SPACE AND REPLACE WITH SAME SIZE COVERED PATIO ENTRY - PER ENGINEER
Permit Issued
Issued on 4/16/2025
Issuing Office
Current Status
CofO Issued on 1/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2024 APPLICANT
Assigned to Plan Check Engineer 5/8/2024 DANIEL ABRAMYAN
Corrections Issued 5/9/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 7/10/2024 DANIEL ABRAMYAN
Plan Check Approved 10/30/2024 DANIEL ABRAMYAN
Plan Check Approved 4/10/2025 DANIEL ABRAMYAN
Issued 4/16/2025 APPLICANT
CofO in Progress 1/22/2026 JUSTIN HAWLEY
Permit Finaled 1/26/2026 DEROLD HAUFF
Permit Finaled 1/26/2026 DEROLD HAUFF
CofO Issued 1/26/2026 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/6/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 6/7/2024 CELINA MORENO
HPOZ Cleared 7/9/2024 DANIEL MATA

Contact Information

Architect Paz, Navas Jose Roberto; Lic. No.: C38895 3665 3RD AVE      LOS ANGELES, CA 90018
Contractor Ochoa Victor Manuel; Lic. No.: 908306-B       ,
Engineer Sandstrom,, Ryan; Lic. No.: NA6364       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/23/2025 Approved ENRIQUE MIRELES
METHANE-Barrier 4/23/2025 Approved ENRIQUE MIRELES
METHANE-Subgrade 4/23/2025 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 5/12/2025 Approved ARTHUR NEGRETE
Deputy Wood Construction 6/3/2025 Conditional Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 6/4/2025 Corrections Issued JUSTIN HAWLEY
BUILDING-Rough-Frame 6/26/2025 Corrections Issued JUSTIN HAWLEY
BUILDING-Rough-Frame 7/25/2025 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 7/25/2025 Approved JUSTIN HAWLEY
Drywall Nailing 7/29/2025 Approved DEVON JACKSON
Interior/Exterior Lathing 7/29/2025 Not Ready for Inspection DEVON JACKSON
Interior/Exterior Lathing 9/15/2025 Partial Inspection WILLIAM SIERRA
Final 1/16/2026 Corrections Issued JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 1/16/2026 SGSOV Approved JUSTIN HAWLEY
ELECTRICAL-Final 1/22/2026 Approved JUSTIN HAWLEY
Final 1/22/2026 OK to Issue CofO JUSTIN HAWLEY
HVAC-Final 1/22/2026 Approved JUSTIN HAWLEY
PLUMBING-Final 1/22/2026 Approved JUSTIN HAWLEY
Smoke Detectors 1/22/2026 Approved JUSTIN HAWLEY