4147 N DIXIE CANYON AVE 91423
Certificate Information: 4147 N DIXIE CANYON AVE 91423
- Application / Permit
- 24014-10000-01848
- Plan Check / Job No.
- B24LA08301
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ***ePlan**Addition and remodel (E) SFD w/ attached Garage
- Permit Issued
- Issued on 7/16/2024
- Issuing Office
- Current Status
- CofO Issued on 4/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2024 | EDWIN ESPIN |
| Corrections Issued | 5/9/2024 | EDWIN ESPIN |
| Plan Check Approved | 6/12/2024 | ALFREDO JARA |
| No Progress | 6/12/2024 | ALFREDO JARA |
| Plan Check Approved | 7/12/2024 | ALFREDO JARA |
| Issued | 7/16/2024 | APPLICANT |
| CofO in Progress | 4/13/2026 | MISAEL ESPARZA |
| CofO Issued | 4/28/2026 | RUBEN SALAS |
| Permit Finaled | 4/28/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2024 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 5/24/2024 | TAL SHEMEN |
| Sewer availability | Cleared | 5/24/2024 | TAL SHEMEN |
| Grading Pre-Inspection | Cleared | 6/12/2024 | AMY GUEVARRA |
Contact Information
| Contractor | B D S Construction Inc; Lic. No.: 614706-B | , |
| Engineer | Quiaot,, Florentino V; Lic. No.: C38659 | 412 W 231ST ST CARSON, CA 90745 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/19/2024 | Partial Approval | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 8/9/2024 | Conditional Approval | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 8/14/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/14/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 8/16/2024 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/16/2024 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 8/26/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 8/28/2024 | Partial Approval | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 8/30/2024 | Approved | MISAEL ESPARZA |
| Wood Frame | 10/3/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 10/11/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Partial Approval | MISAEL ESPARZA |
| Structural Steel Frame | 10/17/2024 | Partial Inspection | MISAEL ESPARZA |
| Wood Frame | 10/17/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Partial Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/19/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/25/2024 | Corrections Issued | JUAN VALENZUELA |
| Interior/Exterior Lathing | 12/2/2024 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/18/2024 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 12/18/2024 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 1/6/2025 | Approved | MISAEL ESPARZA |
| Insulation | 1/7/2025 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 1/17/2025 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 1/29/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/26/2026 | Approved | MISAEL ESPARZA |
| Final | 3/26/2026 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 3/26/2026 | Approved | MISAEL ESPARZA |
| Green Building Rough | 3/26/2026 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 3/26/2026 | Approved | MISAEL ESPARZA |
| Final | 4/9/2026 | OK to Issue CofO | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 4/9/2026 | SGSOV Approved | MISAEL ESPARZA |