3756 N GOODLAND AVE 91604

Certificate Information: 3756 N GOODLAND AVE 91604

Application / Permit
24014-10000-01807
Plan Check / Job No.
B24LA08105
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: MAJOR INTERIOR REMODEL AND 2ND STORY ADDITION TO (E) SFD **NFPA-13D fire sprinklers throughout**
Permit Issued
Issued on 7/2/2024
Issuing Office
Current Status
CofO Issued on 8/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2024 APPLICANT
Assigned to Plan Check Engineer 5/6/2024 MOHAMMAD ESMAILI
Corrections Issued 5/7/2024 MOHAMMAD ESMAILI
Applicant returned to address corrections 6/6/2024 MOHAMMAD ESMAILI
Plan Check Approved 7/1/2024 ISIS ARGUETA
Issued 7/2/2024 APPLICANT
CofO in Progress 7/16/2025 CHRISTOPHE COCHRAN
Permit Finaled 8/5/2025 RUBEN SALAS
CofO Issued 8/5/2025 RUBEN SALAS
Permit Finaled 8/5/2025 RUBEN SALAS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 5/9/2024 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 5/9/2024 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 5/9/2024 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 5/9/2024 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 5/9/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/9/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/9/2024 CARLOS AGUILERA
Sewer availability Cleared 5/9/2024 CARLOS AGUILERA
Grading Pre-Inspection Cleared 5/14/2024 MICHAEL TEMPLE
Distance to fire station Cleared 6/21/2024 GILBERT URREA
Hydrant and Access approval Cleared 6/21/2024 GILBERT URREA
GPI Written Notices Cleared 7/1/2024 MOHAMMAD ESMAILI

Contact Information

Contractor Owner-Builder       ,
Engineer Salahaldin,, Aws; Lic. No.: C95446 100 DESERT LOTUS      IRVINE, CA 92618

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/15/2024 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 8/15/2024 Not Ready for Inspection VINCENT HANLEY
Footing/Foundation/Slab 8/23/2024 No Access for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 8/27/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 9/12/2024 Corrections Issued CHRISTOPHE COCHRAN
Green Building Rough 9/12/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 9/12/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Insulation 9/16/2024 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/3/2024 Corrections Issued CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 12/3/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Rough 12/3/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 12/3/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/11/2024 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 12/11/2024 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 12/11/2024 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 12/11/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 1/9/2025 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 1/9/2025 Approved CHRISTOPHE COCHRAN
HVAC-Rough 1/9/2025 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 1/9/2025 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 1/9/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 2/4/2025 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/6/2025 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 2/6/2025 Approved CHRISTOPHE COCHRAN
Insulation 2/11/2025 Approved JACK KARGODORIAN
Shower Pan 2/11/2025 Approved JACK KARGODORIAN
Drywall Nailing 2/19/2025 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 2/25/2025 Approved CHRISTOPHE COCHRAN
HVAC-Rough 5/16/2025 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 6/11/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Final 6/11/2025 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 6/11/2025 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 6/16/2025 Approved CHRISTOPHE COCHRAN
Final 6/16/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Final 6/16/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 6/16/2025 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 6/16/2025 Approved CHRISTOPHE COCHRAN
Final 7/1/2025 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 7/1/2025 Approved CHRISTOPHE COCHRAN
Final 7/16/2025 OK to Issue CofO CHRISTOPHE COCHRAN