3407 N LIFUR AVE 90032

Certificate Information: 3407 N LIFUR AVE 90032

Application / Permit
24014-10000-01770
Plan Check / Job No.
B24LA07953
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN Convert (E) detached garage into an ADU with addition per ordinance
Permit Issued
Issued on 6/19/2024
Issuing Office
Current Status
CofO Issued on 12/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2024 APPLICANT
Assigned to Plan Check Engineer 5/3/2024 MINA HABILI
Corrections Issued 5/4/2024 MINA HABILI
Plan Check Approved 6/16/2024 MINA HABILI
Issued 6/19/2024 APPLICANT
CofO in Progress 12/3/2024 LILIANA PORTILLO
Permit Finaled 12/7/2024 DEROLD HAUFF
CofO Issued 12/7/2024 DEROLD HAUFF
Permit Finaled 12/7/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/13/2024 AMBER CAMPBELL
Roof/Waste drainage to street Cleared 5/13/2024 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 6/13/2024 AMBER CAMPBELL
Sewer availability Cleared 6/13/2024 AMBER CAMPBELL
Grading Pre-Inspection Cleared 6/16/2024 MINA HABILI

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Preferred Home Builders Inc; Lic. No.: 773147-B       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/4/2024 Approved BRENDAN MORELLI
PLUMBING-Rough 9/4/2024 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 9/27/2024 Partial Approval BRENDAN MORELLI
Rough-Elec/Plmb/HVAC 9/27/2024 Corrections Issued BRENDAN MORELLI
BUILDING-Rough-Frame 10/2/2024 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/2/2024 Partial Approval LILIANA PORTILLO
Rough-Elec/Plmb/HVAC 10/2/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/7/2024 Approved LILIANA PORTILLO
Green Building Rough 10/7/2024 Approved LILIANA PORTILLO
Insulation 10/7/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 10/7/2024 Partial Approval LILIANA PORTILLO
Drywall Nailing 10/10/2024 Not Ready for Inspection LILIANA PORTILLO
Underground Mechanical 10/10/2024 Not Ready for Inspection LILIANA PORTILLO
Drywall Nailing 10/11/2024 Approved LILIANA PORTILLO
Underground Mechanical 10/11/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 10/15/2024 Approved LILIANA PORTILLO
Shower Pan 10/15/2024 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 11/21/2024 Approved LILIANA PORTILLO
Final 11/21/2024 Corrections Issued LILIANA PORTILLO
Green Building Final 11/21/2024 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 11/21/2024 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 11/21/2024 Approved LILIANA PORTILLO
Final 11/25/2024 Not Ready for Inspection LILIANA PORTILLO
Final 12/2/2024 OK to Issue CofO LILIANA PORTILLO
Green Building Final 12/2/2024 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/2/2024 SGSOV Approved LILIANA PORTILLO