412 N AVENUE 50 90042
Certificate Information: 412 N AVENUE 50 90042
- Application / Permit
- 24014-10000-01759
- Plan Check / Job No.
- B24LA07905
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Addition and remodel to existing SFD (front home)
- Permit Issued
- Issued on 6/18/2025
- Issuing Office
- Current Status
- CofO Issued on 11/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 5/16/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 5/24/2024 | TU HUA |
| Applicant returned to address corrections | 8/14/2024 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 9/18/2024 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 10/29/2024 | MARCELA FRANQUEZ |
| Plan Check Approved | 12/6/2024 | MARCELA FRANQUEZ |
| Issued | 6/18/2025 | APPLICANT |
| CofO in Progress | 10/31/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 11/9/2025 | DEROLD HAUFF |
| Permit Finaled | 11/9/2025 | DEROLD HAUFF |
| CofO Issued | 11/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/31/2024 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 7/31/2024 | JOSE HERNANDEZ |
| ZA Case | Cleared | 7/31/2024 | ROSALINDA MEZA |
| Grading Pre-Inspection | Cleared | 8/23/2024 | LANNY MERRICK |
| Specific Plan | Cleared | 9/30/2024 | ANDREA MAGANA-WITHERS |
| Hydrant and Access approval | Cleared | 10/15/2024 | JERRY KAO |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2024 | ABEL CASILLAS |
Contact Information
| Contractor | Jc Builders General Contractors; Lic. No.: 1109358-B | , |
| Engineer | Chikhale,, Jonathan; Lic. No.: C78893 | 2820 MILITARY AVENUE LOS ANGELES, CA 90064 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/30/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 7/11/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/12/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 8/12/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 8/12/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 8/12/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/12/2025 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 8/25/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/25/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/26/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 8/29/2025 | Approved | REGINA MENDEZ |
| Green Building Rough | 8/29/2025 | Approved | REGINA MENDEZ |
| Green Building Final | 9/19/2025 | Not Ready for Inspection | REGINA MENDEZ |
| Interior/Exterior Lathing | 9/19/2025 | Approved | REGINA MENDEZ |
| BUILDING-Rough-Frame | 10/17/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 10/17/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 10/17/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 10/17/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 10/17/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 10/17/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 10/22/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 10/22/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 10/29/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 10/31/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |