4425 N BRUNSWICK AVE 90039

Certificate Information: 4425 N BRUNSWICK AVE 90039

Application / Permit
24014-10000-01757
Plan Check / Job No.
B24LA07888
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 20'-0" x 9'-10.5" AND 3'-0" x 5'-4" ADDITION TO THE (E) SINGLE FAMILY DWELLING AND INTERIOR REMODEL.
Permit Issued
Issued on 5/30/2024
Issuing Office
Current Status
CofO Issued on 2/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2024 APPLICANT
Assigned to Plan Check Engineer 5/7/2024 SARKIS HARABEDIAN
Corrections Issued 5/8/2024 SARKIS HARABEDIAN
Plan Check Approved 5/25/2024 SARKIS HARABEDIAN
Issued 5/30/2024 APPLICANT
CofO in Progress 2/11/2025 THOMAS LOGRASSO
Permit Finaled 2/13/2025 DEROLD HAUFF
Permit Finaled 2/13/2025 DEROLD HAUFF
CofO Issued 2/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/13/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 5/15/2024 TREVOR QUAN

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor L E A D Enterprises Inc; Lic. No.: 955824-B       ,
Contractor Pearl Remodeling; Lic. No.: 955824-B       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/21/2024 Conditional Approval THOMAS LOGRASSO
Footing/Foundation/Slab 8/21/2024 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/5/2024 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 9/5/2024 Approved THOMAS LOGRASSO
PLUMBING-Rough 9/5/2024 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/6/2024 Approved THOMAS LOGRASSO
ELECTRICAL-Rough 9/19/2024 Approved THOMAS LOGRASSO
PLUMBING-Rough 9/19/2024 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/26/2024 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 10/8/2024 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 10/8/2024 Approved THOMAS LOGRASSO
Deputy Wood Construction 10/9/2024 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 10/16/2024 Approved THOMAS LOGRASSO
Insulation 10/16/2024 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 10/16/2024 Approved THOMAS LOGRASSO
Drywall Nailing 11/1/2024 Approved THOMAS LOGRASSO
Insulation 11/1/2024 Approved THOMAS LOGRASSO
Final 2/4/2025 Corrections Issued THOMAS LOGRASSO
Green Building Final 2/4/2025 Approved THOMAS LOGRASSO
Green Building Rough 2/4/2025 Approved THOMAS LOGRASSO
Smoke Detectors 2/4/2025 Approved THOMAS LOGRASSO
Final 2/11/2025 OK to Issue CofO THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 2/11/2025 SGSOV Approved THOMAS LOGRASSO