1830 S POINT VIEW ST 90035

Certificate Information: 1830 S POINT VIEW ST 90035

Application / Permit
24014-10000-01749
Plan Check / Job No.
B24LA07854
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN 1. MAJOR REMODEL AND ADDITION TO (E) SFD. NFPA 13D FIRE SPRINKLERS THROUGH OUT.
Permit Issued
Issued on 8/6/2024
Issuing Office
Current Status
Issued on 8/6/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/29/2024 APPLICANT
Assigned to Plan Check Engineer 5/2/2024 ADRIANA LOPEZ
Corrections Issued 5/5/2024 ADRIANA LOPEZ
Quality Review Completed 5/28/2024 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 7/24/2024 ADRIANA LOPEZ
Plan Check Approved 8/5/2024 ADRIANA LOPEZ
Issued 8/6/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/13/2024 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 5/14/2024 CHRISTINA BRACO
Sewer availability Cleared 5/14/2024 CHRISTINA BRACO

Contact Information

Contractor Rimon Construction Inc; Lic. No.: 1077839-B       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/8/2024 Approved ARTHUR NEGRETE
Footing/Foundation/Slab 8/8/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 8/28/2024 Not Ready for Inspection ARTHUR NEGRETE
Green Building Rough 8/28/2024 Not Ready for Inspection ARTHUR NEGRETE
Underground Mechanical 8/28/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 8/30/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 10/9/2024 Approved ARTHUR NEGRETE
Deputy Wood Construction 10/17/2024 Conditional Approval STUART CHAPMAN
BUILDING-Rough-Frame 11/4/2024 Not Ready for Inspection ARTHUR NEGRETE
ELECTRICAL-Rough 11/4/2024 Approved ARTHUR NEGRETE
Green Building Rough 11/4/2024 Approved ARTHUR NEGRETE
HVAC-Rough 11/4/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 11/4/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 11/5/2024 No Access for Inspection ENRIQUE MIRELES
Green Building Rough 11/5/2024 No Access for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 11/21/2024 Approved ARTHUR NEGRETE
Shower Pan 11/21/2024 Approved ARTHUR NEGRETE
Insulation 11/27/2024 Approved ANTHONY RAMOS
Drywall Nailing 12/4/2024 Approved ARTHUR NEGRETE
Green Building Rough 12/4/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 12/4/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Final 5/28/2025 Approved ARTHUR NEGRETE
Green Building Final 5/28/2025 Conditional Approval ARTHUR NEGRETE
HVAC-Final 5/28/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 5/28/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 6/2/2025 Approved ARTHUR NEGRETE
Final 6/2/2025 Partial Inspection ARTHUR NEGRETE
Green Building Final 6/2/2025 Conditional Approval ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 6/2/2025 SGSOV Approved ARTHUR NEGRETE
Service/Power Release 6/2/2025 Not Ready for Inspection ARTHUR NEGRETE
Smoke Detectors 6/2/2025 Approved ARTHUR NEGRETE
Service/Power Release 6/4/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 1/6/2026 Corrections Issued BRENDAN MORELLI
Special/Order Compliance 1/6/2026 Not Ready for Inspection BRENDAN MORELLI