121 N JUNE ST 90004
Certificate Information: 121 N JUNE ST 90004
- Application / Permit
- 24014-10000-01722
- Plan Check / Job No.
- B24LA07688
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2ND STORY ADDITION AND 2ND FLOOR REMODEL FOR EXISTING SFD
- Permit Issued
- Issued on 7/19/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2024 | CARLOS MONTES |
| Corrections Issued | 5/7/2024 | CARLOS MONTES |
| Quality Review Completed | 5/8/2024 | KEN GILL |
| Building Plans Picked Up | 5/9/2024 | APPLICANT |
| Plan Check Approved | 6/4/2024 | CARLOS MONTES |
| Issued | 7/19/2024 | APPLICANT |
| CofO in Progress | 9/22/2025 | RONNIE MINDANAO |
| Permit Finaled | 9/25/2025 | DEROLD HAUFF |
| CofO Issued | 9/25/2025 | DEROLD HAUFF |
| Permit Finaled | 9/25/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 5/14/2024 | SUKI GERSHENHORN |
| HPOZ | Cleared | 5/14/2024 | SUKI GERSHENHORN |
| Roof/Waste drainage to street | Cleared | 5/16/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 5/17/2024 | TREVOR QUAN |
Contact Information
| Architect | Scrafano,, Elissa F; Lic. No.: C26071 | 163 N SYCAMORE LOS ANGELES, CA 90036 |
| Contractor | Hacienda Lopez Construction Inc; Lic. No.: 910123-B | 1927 LE FLORE DRIVE LA HABRA HEIGHTS, CA 90631 |
| Engineer | Zangoli,, Fabio; Lic. No.: S6191 | 13245 FIJI WY UNIT J MARINA DEL REY, CA 90292 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/21/2024 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 9/11/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 9/11/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 9/11/2024 | Approved | RONNIE MINDANAO |
| Wood Frame | 9/11/2024 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2024 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2024 | Partial Approval | JEFFREY MEAD |
| Deputy Drilled-In Anchors | 11/13/2024 | Conditional Approval | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 11/14/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| ELECTRICAL-Rough | 11/14/2024 | Approved | RONNIE MINDANAO |
| Green Building Rough | 11/14/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Rough | 11/14/2024 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 11/15/2024 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Barrier | 11/15/2024 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 11/15/2024 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 11/19/2024 | Conditional Approval | RONNIE MINDANAO |
| Green Building Rough | 11/19/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Insulation | 12/16/2024 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 1/10/2025 | Conditional Approval | RONNIE MINDANAO |
| Interior/Exterior Lathing | 1/27/2025 | Approved | RONNIE MINDANAO |
| Shower Pan | 1/27/2025 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 2/27/2025 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 3/3/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 8/25/2025 | Approved | RONNIE MINDANAO |
| Final | 8/25/2025 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 8/25/2025 | Approved | RONNIE MINDANAO |
| Green Building Final | 8/25/2025 | Approved | RONNIE MINDANAO |
| Green Building Rough | 8/25/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 8/25/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 8/25/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 8/29/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 8/29/2025 | Approved | RONNIE MINDANAO |
| Final | 9/4/2025 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 9/4/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Final | 9/8/2025 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 9/8/2025 | SGSOV Approved | RONNIE MINDANAO |
| Final | 9/19/2025 | OK to Issue CofO | RONNIE MINDANAO |