10512 W KINNARD AVE 90024

Certificate Information: 10512 W KINNARD AVE 90024

Application / Permit
24014-10000-01716
Plan Check / Job No.
B24LA07593
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
***EPLAN*** CONVERT (E) DETACHED GARAGE AND ADDITION TO (N) DETACHAED ADU PER ORDIANACE
Permit Issued
Issued on 6/18/2024
Issuing Office
Current Status
CofO Issued on 12/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/26/2024 APPLICANT
Assigned to Plan Check Engineer 5/1/2024 FERNANDO FLORES
Corrections Issued 5/2/2024 FERNANDO FLORES
Applicant returned to address corrections 5/23/2024 FERNANDO FLORES
Plan Check Approved 6/17/2024 TSE MING HUANG
Issued 6/18/2024 APPLICANT
CofO in Progress 12/26/2025 MICHAEL ALLEN
Permit Finaled 12/30/2025 RICHARD STEINBACH
CofO Issued 12/30/2025 RICHARD STEINBACH
Permit Finaled 12/30/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/31/2024 BRENDEN HAWK
Roof/Waste drainage to street Cleared 5/31/2024 BRENDEN HAWK
Construction near power lines Cleared 6/6/2024 WALTER RAMIREZ
Construction within easement Cleared 6/6/2024 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 6/7/2024 LIAM ODONOVAN
Sewer availability Cleared 6/7/2024 LIAM ODONOVAN
Specific Plan Cleared 6/13/2024 JOSHUA JONES
Public Works-Highway Ded. Cleared 7/30/2025 CHRISTINE REUSCH
Public Works-Open Permits Cleared 7/30/2025 CHRISTINE REUSCH
Public Works-Sewers Cleared 7/30/2025 CHRISTINE REUSCH

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Armando; Lic. No.: C83911 2000 W LINCOLN AVE      MONTEBELLO, CA 90640

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/3/2024 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 1/23/2025 Corrections Issued KIRK SANDERS
METHANE-Barrier 1/23/2025 Approved KIRK SANDERS
METHANE-Subgrade 1/23/2025 Approved KIRK SANDERS
Excavation/Setback/Form/Re-Bar 1/24/2025 Partial Approval MICHAEL PELHAM
Footing/Foundation/Slab 1/24/2025 Partial Approval MICHAEL PELHAM
Underground Mechanical 1/28/2025 Partial Approval KIRK SANDERS
Deputy Drilled-In Anchors 1/31/2025 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 2/3/2025 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/7/2025 Partial Approval KIRK SANDERS
Wood Frame 3/7/2025 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 3/18/2025 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 3/18/2025 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 3/18/2025 Corrections Issued ARAM AVEDISIAN
Special/Order Compliance 3/18/2025 Partial Inspection MICHAEL PELHAM
ELECTRICAL-Final 3/24/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 3/24/2025 Partial Approval KIRK SANDERS
HVAC-Rough 3/24/2025 Corrections Issued KIRK SANDERS
PLUMBING-Rough 3/24/2025 Partial Approval KIRK SANDERS
Special/Order Compliance 3/26/2025 Partial Inspection DAVID FEILER
BUILDING-Rough-Frame 3/27/2025 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 3/27/2025 Partial Approval KIRK SANDERS
Green Building Rough 3/27/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 3/27/2025 Approved KIRK SANDERS
PLUMBING-Rough 3/27/2025 Corrections Issued KIRK SANDERS
Shower Pan 3/27/2025 Approved KIRK SANDERS
PLUMBING-Rough 4/1/2025 Corrections Issued CARLOS MATAMOROS
BUILDING-Rough-Frame 4/3/2025 Approved KIRK SANDERS
ELECTRICAL-Rough 4/3/2025 Approved KIRK SANDERS
Green Building Rough 4/3/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 4/3/2025 Partial Approval KIRK SANDERS
PLUMBING-Rough 4/3/2025 Approved KIRK SANDERS
Insulation 4/7/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 4/7/2025 Not Ready for Inspection JAYLIN GRAVITTE
Drywall Nailing 4/10/2025 Approved KIRK SANDERS
Interior/Exterior Lathing 4/10/2025 Approved KIRK SANDERS
Final 8/21/2025 Corrections Issued ARAM AVEDISIAN
Green Building Final 8/21/2025 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 8/21/2025 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 8/21/2025 Approved ARAM AVEDISIAN
ELECTRICAL-Final 12/17/2025 Corrections Issued MICHAEL ALLEN
Final 12/17/2025 Not Ready for Inspection MICHAEL ALLEN
HVAC-Final 12/17/2025 Approved MICHAEL ALLEN
PLUMBING-Final 12/17/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 12/17/2025 SGSOV Approved MICHAEL ALLEN
ELECTRICAL-Final 12/24/2025 Approved MICHAEL ALLEN
Final 12/24/2025 OK to Issue CofO MICHAEL ALLEN