10512 W KINNARD AVE 90024
Certificate Information: 10512 W KINNARD AVE 90024
- Application / Permit
- 24014-10000-01716
- Plan Check / Job No.
- B24LA07593
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ***EPLAN*** CONVERT (E) DETACHED GARAGE AND ADDITION TO (N) DETACHAED ADU PER ORDIANACE
- Permit Issued
- Issued on 6/18/2024
- Issuing Office
- Current Status
- CofO Issued on 12/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2024 | FERNANDO FLORES |
| Corrections Issued | 5/2/2024 | FERNANDO FLORES |
| Applicant returned to address corrections | 5/23/2024 | FERNANDO FLORES |
| Plan Check Approved | 6/17/2024 | TSE MING HUANG |
| Issued | 6/18/2024 | APPLICANT |
| CofO in Progress | 12/26/2025 | MICHAEL ALLEN |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
| CofO Issued | 12/30/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/30/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/31/2024 | BRENDEN HAWK |
| Roof/Waste drainage to street | Cleared | 5/31/2024 | BRENDEN HAWK |
| Construction near power lines | Cleared | 6/6/2024 | WALTER RAMIREZ |
| Construction within easement | Cleared | 6/6/2024 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 6/7/2024 | LIAM ODONOVAN |
| Specific Plan | Cleared | 6/13/2024 | JOSHUA JONES |
| Public Works-Highway Ded. | Cleared | 7/30/2025 | CHRISTINE REUSCH |
| Public Works-Open Permits | Cleared | 7/30/2025 | CHRISTINE REUSCH |
| Public Works-Sewers | Cleared | 7/30/2025 | CHRISTINE REUSCH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Armando; Lic. No.: C83911 | 2000 W LINCOLN AVE MONTEBELLO, CA 90640 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/3/2024 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 1/23/2025 | Corrections Issued | KIRK SANDERS |
| METHANE-Barrier | 1/23/2025 | Approved | KIRK SANDERS |
| METHANE-Subgrade | 1/23/2025 | Approved | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 1/24/2025 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 1/24/2025 | Partial Approval | MICHAEL PELHAM |
| Underground Mechanical | 1/28/2025 | Partial Approval | KIRK SANDERS |
| Deputy Drilled-In Anchors | 1/31/2025 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 2/3/2025 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Partial Approval | KIRK SANDERS |
| Wood Frame | 3/7/2025 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 3/18/2025 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Rough | 3/18/2025 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/18/2025 | Corrections Issued | ARAM AVEDISIAN |
| Special/Order Compliance | 3/18/2025 | Partial Inspection | MICHAEL PELHAM |
| ELECTRICAL-Final | 3/24/2025 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 3/24/2025 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 3/24/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 3/24/2025 | Partial Approval | KIRK SANDERS |
| Special/Order Compliance | 3/26/2025 | Partial Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 3/27/2025 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 3/27/2025 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 3/27/2025 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 3/27/2025 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 3/27/2025 | Corrections Issued | KIRK SANDERS |
| Shower Pan | 3/27/2025 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 4/1/2025 | Corrections Issued | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 4/3/2025 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 4/3/2025 | Approved | KIRK SANDERS |
| Green Building Rough | 4/3/2025 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 4/3/2025 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 4/3/2025 | Approved | KIRK SANDERS |
| Insulation | 4/7/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 4/7/2025 | Not Ready for Inspection | JAYLIN GRAVITTE |
| Drywall Nailing | 4/10/2025 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 4/10/2025 | Approved | KIRK SANDERS |
| Final | 8/21/2025 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 8/21/2025 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 8/21/2025 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 8/21/2025 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 12/17/2025 | Corrections Issued | MICHAEL ALLEN |
| Final | 12/17/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| HVAC-Final | 12/17/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 12/17/2025 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 12/17/2025 | SGSOV Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 12/24/2025 | Approved | MICHAEL ALLEN |
| Final | 12/24/2025 | OK to Issue CofO | MICHAEL ALLEN |