8023 S LOYOLA BLVD 90045

Certificate Information: 8023 S LOYOLA BLVD 90045

Application / Permit
24014-10000-01715
Plan Check / Job No.
B24LA07592
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: 1ST FLOOR ADDITION TO (E) RECREATION ROOM WITH ATTACHED GARAGE AND 2ND FLOOR ACCESSORY DWELLING UNIT ADDITION PER LAMC 12.22.A.33.(c)-(e)
Permit Issued
Issued on 9/6/2024
Issuing Office
Current Status
CofO Issued on 6/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 DANIEL YIP
Corrections Issued 5/14/2024 DANIEL YIP
Quality Review Completed 5/28/2024 GARO TELMI
Applicant returned to address corrections 7/2/2024 DANIEL YIP
Applicant returned to address corrections 8/7/2024 DANIEL YIP
Plan Check Approved 9/4/2024 DANIEL YIP
Plan Check Approved 9/6/2024 DANIEL YIP
Issued 9/6/2024 APPLICANT
CofO in Progress 6/24/2025 DAVID FEILER
Permit Finaled 6/26/2025 RICHARD STEINBACH
Permit Finaled 6/26/2025 RICHARD STEINBACH
CofO Issued 6/26/2025 RICHARD STEINBACH

Permit Application Clearance Information

Construction near power lines Cleared 6/3/2024 TINA MIRANDA
Address approval Cleared 6/4/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 6/5/2024 DARIN LAM
Sewer availability Cleared 6/5/2024 DARIN LAM
Roof/Waste drainage to street Cleared 7/23/2024 ANDREA SAINT-ANTONIN
Specific Plan Cleared 8/20/2024 FREDDY GARCIA

Contact Information

Architect Hodgdon,, Emily Elizabeth; Lic. No.: NA30043       ,
Contractor Pagan Robert M Construction Company; Lic. No.: 509594-B       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/25/2024 Conditional Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 12/11/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 12/26/2024 Corrections Issued BOBBY KEY
Special/Order Compliance 12/26/2024 Partial Inspection JAYLIN GRAVITTE
BUILDING-Rough-Frame 2/6/2025 Approved MICHAEL ALLEN
ELECTRICAL-Rough 2/6/2025 Corrections Issued MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 2/6/2025 Partial Approval MICHAEL ALLEN
Green Building Rough 2/6/2025 Approved MICHAEL ALLEN
HVAC-Rough 2/6/2025 Partial Approval MICHAEL ALLEN
METHANE-Rough 2/6/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 2/6/2025 Approved MICHAEL ALLEN
ELECTRICAL-Rough 2/10/2025 Approved TEMISTOCLES CAAL
Special/Order Compliance 2/11/2025 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Rough 2/25/2025 Approved TEMISTOCLES CAAL
Insulation 2/25/2025 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 2/25/2025 Approved TEMISTOCLES CAAL
Shower Pan 2/25/2025 Approved TEMISTOCLES CAAL
Drywall Nailing 3/3/2025 Approved TEMISTOCLES CAAL
Special/Order Compliance 3/3/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 5/30/2025 Corrections Issued JESUS PINEDA
Final 5/30/2025 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 5/30/2025 Approved JESUS PINEDA
Green Building Final 5/30/2025 Corrections Issued JESUS PINEDA
HVAC-Final 5/30/2025 Corrections Issued JESUS PINEDA
PLUMBING-Final 5/30/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 5/30/2025 SGSOV Approved JESUS PINEDA
Smoke Detectors 5/30/2025 Approved JESUS PINEDA
ELECTRICAL-Final 6/16/2025 Approved TEMISTOCLES CAAL
Final 6/16/2025 Corrections Issued TEMISTOCLES CAAL
Green Building Final 6/16/2025 Approved TEMISTOCLES CAAL
HVAC-Final 6/16/2025 Approved TEMISTOCLES CAAL
PLUMBING-Final 6/16/2025 Approved TEMISTOCLES CAAL
Final 6/24/2025 OK to Issue CofO DAVID FEILER
Service/Power Release 6/24/2025 Approved DAVID FEILER