3955 S VICTORIA AVE 90008
Certificate Information: 3955 S VICTORIA AVE 90008
- Application / Permit
- 24014-10000-01709
- Plan Check / Job No.
- B24LA07556
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. ADDITION TO (E) DETACHED ADU. PER ENGINEERING DESIGN.
- Permit Issued
- Issued on 12/5/2024
- Issuing Office
- Current Status
- CofO Issued on 6/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2024 | JOHNPAUL ISIP |
| Corrections Issued | 4/27/2024 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 5/9/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 10/31/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 11/4/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 11/28/2024 | DAVID CASTILLO |
| Plan Check Approved | 12/4/2024 | ALFREDO JARA |
| Issued | 12/5/2024 | APPLICANT |
| CofO in Progress | 6/12/2025 | LUIS CASTRO |
| Permit Finaled | 6/12/2025 | DEROLD HAUFF |
| CofO Issued | 6/12/2025 | DEROLD HAUFF |
| Permit Finaled | 6/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/8/2024 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 6/11/2024 | ADRIAN SANCHEZ |
| Construction near power lines | Cleared | 10/29/2024 | TINA MIRANDA |
Contact Information
| Contractor | Rios Construction; Lic. No.: 1104081-B | , |
| Engineer | Grandhi,, Venkata Rohit; Lic. No.: C88709 | 7823 BOXWOOD CT HIGHLAND, CA 92346 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/9/2025 | Partial Approval | LUIS CASTRO |
| Footing/Foundation/Slab | 1/13/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2025 | Partial Approval | LUIS CASTRO |
| Pre-Inspection | 2/18/2025 | Partial Approval | LUIS CASTRO |
| Wood Frame | 2/18/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 3/10/2025 | Approved | LUIS CASTRO |
| Interior/Exterior Lathing | 3/10/2025 | Approved | LUIS CASTRO |
| Pre-Inspection | 3/10/2025 | Partial Approval | LUIS CASTRO |
| Wood Frame | 3/10/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 3/25/2025 | Corrections Issued | LUIS CASTRO |
| Pre-Inspection | 3/25/2025 | Not Ready for Inspection | LUIS CASTRO |
| Wood Frame | 3/25/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Rough | 4/2/2025 | Approved | LUIS CASTRO |
| Pre-Inspection | 4/2/2025 | Not Ready for Inspection | LUIS CASTRO |
| Wood Frame | 4/2/2025 | Approved | LUIS CASTRO |
| Insulation | 4/29/2025 | Approved | LUIS CASTRO |
| Drywall Nailing | 5/7/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 6/9/2025 | Approved | LUIS CASTRO |
| Final | 6/9/2025 | Partial Approval | LUIS CASTRO |
| Green Building Final | 6/9/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 6/9/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 6/9/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 6/9/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 6/11/2025 | Approved | LUIS CASTRO |
| Final | 6/11/2025 | OK to Issue CofO | LUIS CASTRO |
| HVAC-Final | 6/11/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 6/11/2025 | Approved | LUIS CASTRO |