1632 S ELLSMERE AVE 90019
Certificate Information: 1632 S ELLSMERE AVE 90019
- Application / Permit
- 24014-10000-01672
- Plan Check / Job No.
- B24LA07425
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan 1st story kitchen remodel and addition. 2nd story addition to existing SFD
- Permit Issued
- Issued on 6/26/2024
- Issuing Office
- Current Status
- CofO Issued on 5/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 5/16/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 5/17/2024 | GARO TELMI |
| Applicant returned to address corrections | 6/5/2024 | MARCELA FRANQUEZ |
| Plan Check Approved | 6/25/2024 | MARCELA FRANQUEZ |
| Issued | 6/26/2024 | APPLICANT |
| CofO in Progress | 10/1/2025 | ARTHUR NEGRETE |
| No Progress | 10/8/2025 | DEROLD HAUFF |
| CofO in Progress | 10/8/2025 | DEROLD HAUFF |
| Permit Finaled | 5/19/2026 | DEROLD HAUFF |
| CofO Issued | 5/19/2026 | DEROLD HAUFF |
| Permit Finaled | 5/19/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/21/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 5/21/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2024 | JESSICA OPINION |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | , |
| Engineer | Messiha,, Hany Gamil; Lic. No.: NA56766 | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/30/2024 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/30/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Barrier | 8/30/2024 | Approved | ARTHUR NEGRETE |
| METHANE-Subgrade | 8/30/2024 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 9/3/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 9/3/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 9/3/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Wood Frame | 9/5/2024 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 10/2/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Rough-Elec/Plmb/HVAC | 10/11/2024 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 10/16/2024 | Approved | ARTHUR NEGRETE |
| Insulation | 10/16/2024 | Approved | ARTHUR NEGRETE |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2024 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 10/30/2024 | Not Ready for Inspection | ANTHONY RAMOS |
| Shower Pan | 10/30/2024 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 11/5/2024 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 11/12/2024 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 11/12/2024 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 12/12/2024 | Approved | JOSE MACIAS |
| Final | 12/12/2024 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 12/12/2024 | Approved | JOSE MACIAS |
| METHANE-Final | 12/12/2024 | Approved | JOSE MACIAS |
| METHANE-Rough | 12/12/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 12/12/2024 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 12/12/2024 | Approved | JOSE MACIAS |
| Final | 12/18/2024 | Corrections Issued | ARTHUR NEGRETE |
| ELECTRICAL-Final | 12/20/2024 | Approved | LUIS CASTRO |
| HVAC-Final | 12/20/2024 | Approved | LUIS CASTRO |
| PLUMBING-Final | 12/20/2024 | Approved | LUIS CASTRO |
| Final | 9/26/2025 | No Access for Inspection | OSVALDO PARAMO |
| Final | 9/30/2025 | OK to Issue CofO | ARTHUR NEGRETE |
| Special/Order Compliance | 2/2/2026 | Corrections Issued | BRENDAN MORELLI |