10353 N WOODMAN AVE 91345

Certificate Information: 10353 N WOODMAN AVE 91345

Application / Permit
24014-10000-01660
Plan Check / Job No.
B24LA07381
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) STORAGE, (E) REC ROOM AND (E) CARPORT INTO ADU WITH ADDITION PER ORDINANCE
Permit Issued
Issued on 10/15/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2024 APPLICANT
Assigned to Plan Check Engineer 4/26/2024 MINA HABILI
Corrections Issued 4/26/2024 MINA HABILI
Building Plans Picked Up 4/29/2024 APPLICANT
Plan Check Approved 10/15/2024 ALEXANDER JOO
Issued 10/15/2024 APPLICANT
CofO in Progress 4/8/2025 JENNIFER RABUCHIN
Permit Finaled 4/24/2025 RUBEN SALAS
CofO Issued 4/24/2025 RUBEN SALAS
Permit Finaled 4/24/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/2/2024 TAL SHEMEN
Roof/Waste drainage to street Cleared 6/2/2024 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 6/3/2024 TAL SHEMEN
Sewer availability Cleared 6/3/2024 TAL SHEMEN
Construction within easement Cleared 9/25/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/21/2024 Corrections Issued JENNIFER RABUCHIN
Deputy Drilled-In Anchors 10/25/2024 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 10/28/2024 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 10/28/2024 Approved JENNIFER RABUCHIN
PLUMBING-Rough 11/22/2024 Partial Approval MICHEL ABAJAN
Sewer 11/22/2024 Approved MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 12/6/2024 Approved ROBERTO PALACIOS-LOPEZ
Gas Test 12/11/2024 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 12/11/2024 Partial Approval JENNIFER RABUCHIN
Gas Test 12/13/2024 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/18/2024 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/31/2024 Not Ready for Inspection JENNIFER RABUCHIN
Deputy Drilled-In Anchors 12/31/2024 Conditional Approval ROBERT GOLD
ELECTRICAL-Rough 12/31/2024 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 12/31/2024 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 12/31/2024 Partial Inspection JENNIFER RABUCHIN
PLUMBING-Rough 12/31/2024 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/10/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 1/10/2025 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 1/10/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 1/10/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 1/21/2025 Approved MATTHEW NELSON
HVAC-Rough 1/21/2025 Approved MATTHEW NELSON
Gas Test 1/23/2025 Partial Approval JENNIFER RABUCHIN
Insulation 1/23/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 1/28/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 2/7/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/3/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/3/2025 Corrections Issued JENNIFER RABUCHIN
Final 4/3/2025 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 4/3/2025 Approved JENNIFER RABUCHIN
Green Building Rough 4/3/2025 Approved JENNIFER RABUCHIN
HVAC-Final 4/3/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/3/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/3/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 4/3/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/7/2025 Approved JENNIFER RABUCHIN
Final 4/7/2025 OK to Issue CofO JENNIFER RABUCHIN
PLUMBING-Final 4/7/2025 Approved JENNIFER RABUCHIN