160 1/2 W 51ST ST 90037

Certificate Information: 160 1/2 W 51ST ST 90037

Application / Permit
24014-10000-01641
Plan Check / Job No.
B24LA07291
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE AND ADDITION TO ACCESSORY DWELLING UNIT PER ORDINANCE . WORK PER WFPP .
Permit Issued
Issued on 6/10/2024
Issuing Office
Metro
Current Status
Issued on 6/10/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/19/2024 APPLICANT
Assigned to Plan Check Engineer 4/22/2024 AUNG SOE
Corrections Issued 4/29/2024 AUNG SOE
Building Plans Picked Up 5/2/2024 APPLICANT
Plan Check Approved 6/10/2024 GEORGE ALVAREZ
Issued 6/10/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/3/2024 ANTHONY TRAN
Eng Process Fee Ord 176,300 Cleared 6/5/2024 ANTHONY TRAN
Roof/Waste drainage to street Cleared 6/5/2024 ANTHONY TRAN
Sewer availability Cleared 6/5/2024 ANTHONY TRAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 7/31/2024 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 7/31/2024 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 8/5/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 8/5/2024 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 8/13/2024 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 8/13/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/2/2024 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 10/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/24/2024 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 10/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/1/2024 Approved JOAQUIN GREENOUGH
HVAC-Rough 11/1/2024 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 11/1/2024 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 11/13/2024 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 12/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/11/2024 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/13/2024 Partial Approval ALEJANDRO DE ARTOLA
Wood Frame 1/10/2025 Corrections Issued BARRY HACHE
Wood Frame 1/15/2025 No Access for Inspection JOHN QUINTANILLA
Wood Frame 2/4/2025 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 2/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 2/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 3/11/2025 Approved ALEJANDRO DE ARTOLA
Wood Frame 3/11/2025 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 4/1/2025 Corrections Issued ANTHONY RAMOS
Drywall Nailing 4/4/2025 Approved ANTHONY RAMOS
Service/Power Release 6/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 6/25/2025 Corrections Issued SABAS ALONSO
HVAC-Final 8/12/2025 Corrections Issued SABAS ALONSO
Service/Power Release 8/12/2025 Corrections Issued SABAS ALONSO
HVAC-Final 8/14/2025 Approved LUIS CASTRO
Service/Power Release 8/14/2025 Not Ready for Inspection LUIS CASTRO
BUILDING-Rough-Frame 9/9/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 9/9/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 9/9/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 9/9/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 9/9/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 9/9/2025 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 9/9/2025 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 9/10/2025 Approved ALEJANDRO DE ARTOLA
Green Building Final 9/10/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 11/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 11/25/2025 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 11/25/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/9/2025 Approved ALEJANDRO DE ARTOLA
Final 12/9/2025 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 12/9/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/11/2025 Corrections Issued ALEJANDRO DE ARTOLA