1706 S SHERBOURNE DR 90035

Certificate Information: 1706 S SHERBOURNE DR 90035

Application / Permit
24014-10000-01640
Plan Check / Job No.
B24LA07290
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: Ground addition (Converet (E) Den and Porch) and remodel to existing 1-story SFD "COMPLY WITH DEPARTMENT ORDER effective date 11/03/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 10/30/2024
Issuing Office
Current Status
Issued on 10/30/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/21/2024 APPLICANT
Assigned to Plan Check Engineer 5/2/2024 KHEDER ALRAZAA
Corrections Issued 5/10/2024 KHEDER ALRAZAA
Quality Review Completed 5/21/2024 GARO TELMI
Applicant returned to address corrections 7/8/2024 KHEDER ALRAZAA
Applicant returned to address corrections 9/12/2024 KHEDER ALRAZAA
Applicant returned to address corrections 10/2/2024 KHEDER ALRAZAA
Plan Check Approved 10/11/2024 KHEDER ALRAZAA
Issued 10/30/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/28/2024 JUSTIN BICOL
Sewer availability Cleared 6/28/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 7/9/2024 JUSTIN BICOL

Contact Information

Contractor Owner-Builder       ,
Engineer Habibi,, Shayaan; Lic. No.: C94225 10535 WILSHIRE BLVD APT 1602      LOS ANGELES, CA 90024

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/26/2024 Approved PETER RUBIO
Deputy Drilled-In Anchors 12/17/2024 Conditional Approval PETER RUBIO
Excavation/Setback/Form/Re-Bar 12/18/2024 Not Ready for Inspection PETER RUBIO
Excavation/Setback/Form/Re-Bar 1/14/2025 Not Ready for Inspection PETER RUBIO
Footing/Foundation/Slab 1/14/2025 Not Ready for Inspection PETER RUBIO
METHANE-Barrier 1/14/2025 Not Ready for Inspection PETER RUBIO
METHANE-Subgrade 1/14/2025 Not Ready for Inspection PETER RUBIO
Excavation/Setback/Form/Re-Bar 1/24/2025 Approved RUBEN PEREZ
Excavation/Setback/Form/Re-Bar 7/3/2025 Corrections Issued ROBERT CHAVEZ
Excavation/Setback/Form/Re-Bar 7/7/2025 Approved RUBEN PEREZ
Deputy Reinf. Concrete 7/11/2025 Conditional Approval PETER RUBIO
BUILDING-Rough-Frame 2/3/2026 Not Ready for Inspection PETER RUBIO
ELECTRICAL-Rough 2/3/2026 Approved PETER RUBIO
Floor/Roof Diaphrgm/Shear Wall 2/3/2026 Approved PETER RUBIO
Green Building Rough 2/3/2026 Not Ready for Inspection PETER RUBIO
HVAC-Rough 2/3/2026 Approved PETER RUBIO
METHANE-Rough 2/3/2026 Approved PETER RUBIO
PLUMBING-Rough 2/3/2026 Approved PETER RUBIO
Rough-Elec/Plmb/HVAC 2/3/2026 Approved PETER RUBIO
Wood Frame 2/3/2026 Not Ready for Inspection PETER RUBIO
Floor/Roof Diaphrgm/Shear Wall 2/10/2026 Approved PETER RUBIO
Insulation 2/10/2026 Approved PETER RUBIO
Interior/Exterior Lathing 2/10/2026 Approved PETER RUBIO
Shower Pan 2/10/2026 Approved PETER RUBIO
Drywall Nailing 2/17/2026 Approved RUBEN PEREZ
Green Building Rough 2/17/2026 Approved RUBEN PEREZ
Interior/Exterior Lathing 3/2/2026 Approved RUBEN PEREZ