17337 W TIARA ST 91316

Certificate Information: 17337 W TIARA ST 91316

Application / Permit
24014-10000-01613
Plan Check / Job No.
B24LA07189
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND ADDITION TO (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE NFPA 13D SPRINKLERED THROUGH OUT
Permit Issued
Issued on 1/7/2025
Issuing Office
Current Status
Issued on 1/7/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/18/2024 APPLICANT
Assigned to Plan Check Engineer 5/2/2024 JAD BASMA
Corrections Issued 5/10/2024 JAD BASMA
Quality Review Completed 5/10/2024 GARO TELMI
Applicant returned to address corrections 10/23/2024 JAD BASMA
Applicant returned to address corrections 11/1/2024 JAD BASMA
Plan Check Approved 11/20/2024 JAD BASMA
No Progress 12/10/2024 JAD BASMA
Plan Check Approved 12/10/2024 JAD BASMA
Issued 1/7/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/21/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/22/2024 BIAINA HARITUNIAN
Sewer availability Cleared 5/22/2024 BIAINA HARITUNIAN
ZI Cleared 8/27/2024 ASHLEY RODARTE
Hydrant and Access approval Cleared 10/8/2024 JERRY KAO

Contact Information

Architect Di, Zitti, Fernando; Lic. No.: NA24587       ,
Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/18/2025 Conditional Approval MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 2/19/2025 Corrections Issued MORRIS JACKSON
Grounding or Bonding 2/19/2025 Approved MORRIS JACKSON
Footing/Foundation/Slab 2/21/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 3/20/2025 Partial Approval MORRIS JACKSON
Wood Frame 3/20/2025 Not Ready for Inspection MORRIS JACKSON
Gas Test 4/7/2025 Approved MORRIS JACKSON
PLUMBING-Rough 4/7/2025 Partial Approval MORRIS JACKSON
Sewer 4/7/2025 Approved MORRIS JACKSON
Insulation 4/9/2025 Partial Approval SEAN WIRCH
Deputy Drilled-In Anchors 4/10/2025 Conditional Approval ROBERT GOLD
ELECTRICAL-Rough 4/14/2025 Partial Approval MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 4/14/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 4/14/2025 Partial Approval MORRIS JACKSON
Deputy Wood Construction 5/14/2025 Conditional Approval MORRIS JACKSON
BUILDING-Rough-Frame 5/20/2025 Not Ready for Inspection MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 5/20/2025 Partial Approval MORRIS JACKSON
Green Building Rough 5/20/2025 Not Ready for Inspection MORRIS JACKSON
BUILDING-Rough-Frame 12/23/2025 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 12/23/2025 Corrections Issued JON MCHUGH
HVAC-Rough 12/23/2025 Approved JON MCHUGH
Interior/Exterior Lathing 12/23/2025 Partial Approval JON MCHUGH
PLUMBING-Rough 12/23/2025 Approved JON MCHUGH
BUILDING-Rough-Frame 1/8/2026 Corrections Issued MORRIS JACKSON
ELECTRICAL-Rough 1/8/2026 Approved MORRIS JACKSON
Green Building Rough 1/8/2026 Approved MORRIS JACKSON
Insulation 1/8/2026 Approved MORRIS JACKSON
Shower Pan 1/8/2026 Approved MORRIS JACKSON
Verify Sprinkler Sign Off 1/8/2026 Approved MORRIS JACKSON
BUILDING-Rough-Frame 1/13/2026 Approved MORRIS JACKSON
Interior/Exterior Lathing 1/13/2026 Approved MORRIS JACKSON
Drywall Nailing 1/23/2026 Approved MORRIS JACKSON
ELECTRICAL-Final 6/3/2026 Corrections Issued IVAN SARABIA
SGSOV-Seismic Gas S/O Valve 6/3/2026 SGSOV Approved IVAN SARABIA
Special/Order Compliance 6/3/2026 Partial Inspection ROBERT GOLD
Service/Power Release 6/9/2026 Approved ROBERT GOLD