13751 N MARCHANT AVE 91342
Certificate Information: 13751 N MARCHANT AVE 91342
- Application / Permit
- 24014-10000-01612
- Plan Check / Job No.
- B24LA07179
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) SFD
- Permit Issued
- Issued on 6/6/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | MINA HABILI |
| Corrections Issued | 4/20/2024 | MINA HABILI |
| Building Plans Picked Up | 4/23/2024 | APPLICANT |
| Plan Check Approved | 5/31/2024 | FERNANDO FLORES |
| Issued | 6/6/2024 | APPLICANT |
| CofO in Progress | 2/14/2025 | KEVIN BERBERYAN |
| No Progress | 2/19/2025 | ROBERT GOLD |
| CofO in Progress | 2/19/2025 | ROBERT GOLD |
| CofO in Progress | 4/10/2025 | RAUL OLAGI |
| CofO in Progress | 4/10/2025 | RAUL OLAGI |
| No Progress | 4/10/2025 | RAUL OLAGI |
| CofO in Progress | 4/10/2025 | RAUL OLAGI |
| Permit Finaled | 4/15/2025 | RUBEN SALAS |
| CofO Issued | 4/15/2025 | RUBEN SALAS |
| Permit Finaled | 4/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/22/2024 | MINA HABILI |
| Roof/Waste drainage to street | Cleared | 5/8/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 5/23/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rahman,, Moksudur; Lic. No.: C69263 | 14616 MCKENDREE AVE CHINO, CA 91708 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/15/2024 | Corrections Issued | KEVIN BERBERYAN |
| Pre-Inspection | 8/15/2024 | Partial Inspection | KEVIN BERBERYAN |
| Sewer | 8/15/2024 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 8/15/2024 | Approved | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 8/21/2024 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2024 | Approved | KEVIN BERBERYAN |
| Deputy Wood Construction | 9/25/2024 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 10/1/2024 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 10/1/2024 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Rough | 10/1/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 10/1/2024 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 10/8/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 10/8/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 10/8/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 10/16/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 10/16/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 10/16/2024 | Approved | KEVIN BERBERYAN |
| Insulation | 10/21/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 10/30/2024 | Approved | KEVIN BERBERYAN |
| Shower Pan | 11/1/2024 | Corrections Issued | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/8/2024 | Approved | KEVIN BERBERYAN |
| Shower Pan | 11/8/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 1/28/2025 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Final | 1/28/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 1/28/2025 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 1/28/2025 | Approved | KEVIN BERBERYAN |
| Green Building Final | 1/28/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 1/28/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Final | 1/28/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 1/28/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 1/28/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 1/28/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 2/11/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 2/11/2025 | Approved | KEVIN BERBERYAN |
| Final | 2/11/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Special/Order Compliance | 3/28/2025 | Partial Inspection | KEVIN BERBERYAN |