339 N KINGS ROAD 90048

Certificate Information: 339 N KINGS ROAD 90048

Application / Permit
24014-10000-01582
Plan Check / Job No.
B24LA07072
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERT (E) DETACHED 2-CAR CARPORT TO ADU PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 6/17/2024
Issuing Office
Current Status
CofO Issued on 8/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/17/2024 APPLICANT
Assigned to Plan Check Engineer 4/19/2024 JOHNPAUL ISIP
Corrections Issued 4/20/2024 JOHNPAUL ISIP
Applicant returned to address corrections 5/8/2024 JOHNPAUL ISIP
Plan Check Approved 6/2/2024 EDWIN ESPIN
Issued 6/17/2024 APPLICANT
CofO in Progress 8/15/2025 JOSE MACIAS
No Progress 8/20/2025 RAUL BARAJAS
CofO in Progress 8/20/2025 RAUL BARAJAS
Permit Finaled 8/29/2025 DEROLD HAUFF
CofO Issued 8/29/2025 DEROLD HAUFF
Permit Finaled 8/29/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/22/2024 DAVID LOPEZ
Roof/Waste drainage to street Cleared 4/22/2024 DAVID LOPEZ
Sewer availability Cleared 4/22/2024 DAVID LOPEZ
Construction within easement Cleared 4/26/2024 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 4/30/2024 CHRISTINA BRACO

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/13/2024 Partial Inspection BRENDAN MORELLI
Underground Mechanical 9/5/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 12/19/2024 Approved ENRIQUE MIRELES
PLUMBING-Rough 12/19/2024 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 12/23/2024 Not Ready for Inspection JOSE MACIAS
ELECTRICAL-Rough 12/27/2024 Approved JOSE MACIAS
HVAC-Rough 12/27/2024 Approved JOSE MACIAS
ELECTRICAL-Rough 1/7/2025 Approved JOSE MACIAS
HVAC-Rough 1/7/2025 Approved JOSE MACIAS
BUILDING-Rough-Frame 1/21/2025 Not Ready for Inspection JOSE MACIAS
Green Building Rough 1/21/2025 Not Ready for Inspection JOSE MACIAS
Interior/Exterior Lathing 1/21/2025 Not Ready for Inspection JOSE MACIAS
METHANE-Rough 1/21/2025 Approved JOSE MACIAS
Insulation 1/27/2025 Approved JOSE MACIAS
Interior/Exterior Lathing 1/27/2025 Approved JOSE MACIAS
Drywall Nailing 2/3/2025 Approved JOSE MACIAS
Shower Pan 2/3/2025 Approved JOSE MACIAS
Interior/Exterior Lathing 2/5/2025 Approved JOSE MACIAS
Sewer 2/26/2025 Not Ready for Inspection JOSE MACIAS
Underground Mechanical 5/14/2025 Partial Approval BRENDAN MORELLI
ELECTRICAL-Final 7/2/2025 Not Ready for Inspection JOSE MACIAS
HVAC-Final 7/2/2025 Not Ready for Inspection JOSE MACIAS
PLUMBING-Final 7/2/2025 Not Ready for Inspection JOSE MACIAS
ELECTRICAL-Final 7/8/2025 Corrections Issued JOSE MACIAS
HVAC-Final 7/8/2025 Corrections Issued JOSE MACIAS
PLUMBING-Final 7/8/2025 Corrections Issued JOSE MACIAS
BUILDING-Rough-Frame 7/28/2025 Approved JOSE MACIAS
ELECTRICAL-Final 7/28/2025 Approved JOSE MACIAS
Final 7/28/2025 Corrections Issued JOSE MACIAS
Footing/Foundation/Slab 7/28/2025 Approved JOSE MACIAS
Green Building Final 7/28/2025 Approved JOSE MACIAS
Green Building Rough 7/28/2025 Approved JOSE MACIAS
HVAC-Final 7/28/2025 Approved JOSE MACIAS
METHANE-Barrier 7/28/2025 Approved JOSE MACIAS
METHANE-Subgrade 7/28/2025 Approved JOSE MACIAS
PLUMBING-Final 7/28/2025 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 7/28/2025 SGSOV Approved JOSE MACIAS
Smoke Detectors 7/28/2025 Approved JOSE MACIAS
Final 8/1/2025 OK to Issue CofO JOSE MACIAS
Service/Power Release 8/1/2025 Not Ready for Inspection JOSE MACIAS