339 N KINGS ROAD 90048
Certificate Information: 339 N KINGS ROAD 90048
- Application / Permit
- 24014-10000-01582
- Plan Check / Job No.
- B24LA07072
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN CONVERT (E) DETACHED 2-CAR CARPORT TO ADU PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/17/2024
- Issuing Office
- Current Status
- CofO Issued on 8/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/19/2024 | JOHNPAUL ISIP |
| Corrections Issued | 4/20/2024 | JOHNPAUL ISIP |
| Applicant returned to address corrections | 5/8/2024 | JOHNPAUL ISIP |
| Plan Check Approved | 6/2/2024 | EDWIN ESPIN |
| Issued | 6/17/2024 | APPLICANT |
| CofO in Progress | 8/15/2025 | JOSE MACIAS |
| No Progress | 8/20/2025 | RAUL BARAJAS |
| CofO in Progress | 8/20/2025 | RAUL BARAJAS |
| Permit Finaled | 8/29/2025 | DEROLD HAUFF |
| CofO Issued | 8/29/2025 | DEROLD HAUFF |
| Permit Finaled | 8/29/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 4/22/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 4/22/2024 | DAVID LOPEZ |
| Construction within easement | Cleared | 4/26/2024 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2024 | CHRISTINA BRACO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/13/2024 | Partial Inspection | BRENDAN MORELLI |
| Underground Mechanical | 9/5/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2024 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/19/2024 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 12/23/2024 | Not Ready for Inspection | JOSE MACIAS |
| ELECTRICAL-Rough | 12/27/2024 | Approved | JOSE MACIAS |
| HVAC-Rough | 12/27/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 1/7/2025 | Approved | JOSE MACIAS |
| HVAC-Rough | 1/7/2025 | Approved | JOSE MACIAS |
| BUILDING-Rough-Frame | 1/21/2025 | Not Ready for Inspection | JOSE MACIAS |
| Green Building Rough | 1/21/2025 | Not Ready for Inspection | JOSE MACIAS |
| Interior/Exterior Lathing | 1/21/2025 | Not Ready for Inspection | JOSE MACIAS |
| METHANE-Rough | 1/21/2025 | Approved | JOSE MACIAS |
| Insulation | 1/27/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 1/27/2025 | Approved | JOSE MACIAS |
| Drywall Nailing | 2/3/2025 | Approved | JOSE MACIAS |
| Shower Pan | 2/3/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 2/5/2025 | Approved | JOSE MACIAS |
| Sewer | 2/26/2025 | Not Ready for Inspection | JOSE MACIAS |
| Underground Mechanical | 5/14/2025 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Final | 7/2/2025 | Not Ready for Inspection | JOSE MACIAS |
| HVAC-Final | 7/2/2025 | Not Ready for Inspection | JOSE MACIAS |
| PLUMBING-Final | 7/2/2025 | Not Ready for Inspection | JOSE MACIAS |
| ELECTRICAL-Final | 7/8/2025 | Corrections Issued | JOSE MACIAS |
| HVAC-Final | 7/8/2025 | Corrections Issued | JOSE MACIAS |
| PLUMBING-Final | 7/8/2025 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 7/28/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 7/28/2025 | Approved | JOSE MACIAS |
| Final | 7/28/2025 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 7/28/2025 | Approved | JOSE MACIAS |
| Green Building Final | 7/28/2025 | Approved | JOSE MACIAS |
| Green Building Rough | 7/28/2025 | Approved | JOSE MACIAS |
| HVAC-Final | 7/28/2025 | Approved | JOSE MACIAS |
| METHANE-Barrier | 7/28/2025 | Approved | JOSE MACIAS |
| METHANE-Subgrade | 7/28/2025 | Approved | JOSE MACIAS |
| PLUMBING-Final | 7/28/2025 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 7/28/2025 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 7/28/2025 | Approved | JOSE MACIAS |
| Final | 8/1/2025 | OK to Issue CofO | JOSE MACIAS |
| Service/Power Release | 8/1/2025 | Not Ready for Inspection | JOSE MACIAS |