3787 N AMESBURY ROAD 90027
Certificate Information: 3787 N AMESBURY ROAD 90027
- Application / Permit
- 24014-10000-01571
- Plan Check / Job No.
- B24LA06993
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Interior remodel and two story addition to (E) 1-story single family dwelling with attached 2-car garage
- Permit Issued
- Issued on 10/22/2024
- Issuing Office
- Current Status
- Issued on 10/22/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | JAD BASMA |
| Corrections Issued | 4/21/2024 | JAD BASMA |
| Quality Review Completed | 4/26/2024 | GARO TELMI |
| Applicant returned to address corrections | 6/27/2024 | JAD BASMA |
| Applicant returned to address corrections | 10/4/2024 | JAD BASMA |
| Plan Check Approved | 10/17/2024 | JAD BASMA |
| Issued | 10/22/2024 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 6/6/2024 | CHRISTINA BRACO |
| BHO/Hillside ordinance | Cleared | 6/6/2024 | CHRISTINA BRACO |
| BHO/Hillside ordinance | Cleared | 6/6/2024 | CHRISTINA BRACO |
| BHO/Hillside ordinance | Cleared | 6/6/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 6/6/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2024 | CHRISTINA BRACO |
| BHO/Hillside ordinance | Cleared | 8/27/2024 | ALBERT TAM |
| Roof/Waste drainage to street | Cleared | 8/27/2024 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 9/19/2024 | GILBERT URREA |
| GPI Written Notices | Cleared | 10/17/2024 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 10/17/2024 | JAD BASMA |
Contact Information
| Contractor | Castillo'S Building & Remodeling Inc; Lic. No.: 1087447-B | , |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/12/2024 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 1/14/2025 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 1/28/2025 | Approved | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2025 | Corrections Issued | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 5/14/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 5/14/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/14/2025 | Approved | ENRIQUE MIRELES |
| Deputy Steel/Welding | 5/15/2025 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2025 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 5/20/2025 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 5/20/2025 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2025 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/30/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 6/12/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 6/17/2025 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 6/20/2025 | Partial Approval | ENRIQUE MIRELES |
| Shower Pan | 7/1/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/7/2025 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 7/21/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 1/22/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 1/22/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 1/22/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Final | 1/22/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 1/22/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 1/22/2026 | SGSOV Not Ready | ENRIQUE MIRELES |
| Smoke Detectors | 1/22/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 1/28/2026 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 1/28/2026 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 1/28/2026 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 2/10/2026 | Partial Approval | ENRIQUE MIRELES |
| Final | 2/10/2026 | Partial Inspection | ENRIQUE MIRELES |
| Green Building Final | 2/10/2026 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 2/10/2026 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 2/10/2026 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 2/10/2026 | Approved | ENRIQUE MIRELES |