3965 S 3RD AVE 90008
Certificate Information: 3965 S 3RD AVE 90008
- Application / Permit
- 24014-10000-01554
- Plan Check / Job No.
- B24LA06936
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 21'-4" X 21'-6" A.D.U. ADDITION TO (E) GARAGE PER STATE LAW.
- Permit Issued
- Issued on 8/20/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 4/19/2024 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 4/23/2024 | APPLICANT |
| Applicant returned to address corrections | 6/3/2024 | JOHN MESIAS |
| Plan Check Approved | 8/19/2024 | JOHN MESIAS |
| Issued | 8/20/2024 | APPLICANT |
| CofO in Progress | 4/24/2025 | LUIS CASTRO |
| Permit Finaled | 4/25/2025 | DEROLD HAUFF |
| CofO Issued | 4/25/2025 | DEROLD HAUFF |
| Permit Finaled | 4/25/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/10/2024 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 5/10/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 5/22/2024 | TREVOR QUAN |
| Construction near power lines | Cleared | 8/14/2024 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2024 | CHRISTINA BRACO |
Contact Information
| Contractor | Cgs Home Improvement Inc; Lic. No.: 1037939-B | 7189 N FIGUEROA ST LOS ANGELES, CA 90042 |
| Engineer | Nagovitsyn,, Evgeny; Lic. No.: C93527 | 17436 ARMINTA ST NORTHRIDGE, CA 91325 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/5/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 9/5/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 9/9/2024 | Partial Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/13/2024 | Corrections Issued | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 9/17/2024 | Conditional Approval | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/18/2024 | Approved | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 10/22/2024 | Partial Inspection | CRAIG DAVIS |
| Sewer | 10/22/2024 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 10/30/2024 | Conditional Approval | BARRY HACHE |
| Rough-Elec/Plmb/HVAC | 10/30/2024 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2024 | Approved | BARRY HACHE |
| Shower Pan | 11/5/2024 | Not Ready for Inspection | BARRY HACHE |
| Interior/Exterior Lathing | 11/20/2024 | Not Ready for Inspection | JOSH MEISTER |
| Shower Pan | 11/20/2024 | Approved | JOSH MEISTER |
| Insulation | 12/3/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 12/3/2024 | Approved | JOSH MEISTER |
| Drywall Nailing | 1/21/2025 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 3/21/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 3/21/2025 | Approved | LUIS CASTRO |
| Final | 3/21/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 3/21/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 3/21/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 3/21/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 3/21/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 3/21/2025 | SGSOV Not Required | LUIS CASTRO |
| Smoke Detectors | 3/21/2025 | Approved | LUIS CASTRO |
| Final | 4/23/2025 | OK to Issue CofO | LUIS CASTRO |