3965 S 3RD AVE 90008

Certificate Information: 3965 S 3RD AVE 90008

Application / Permit
24014-10000-01554
Plan Check / Job No.
B24LA06936
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 21'-4" X 21'-6" A.D.U. ADDITION TO (E) GARAGE PER STATE LAW.
Permit Issued
Issued on 8/20/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/16/2024 APPLICANT
Assigned to Plan Check Engineer 4/18/2024 LAWRENCE QUIRANTE
Corrections Issued 4/19/2024 LAWRENCE QUIRANTE
Building Plans Picked Up 4/23/2024 APPLICANT
Applicant returned to address corrections 6/3/2024 JOHN MESIAS
Plan Check Approved 8/19/2024 JOHN MESIAS
Issued 8/20/2024 APPLICANT
CofO in Progress 4/24/2025 LUIS CASTRO
Permit Finaled 4/25/2025 DEROLD HAUFF
CofO Issued 4/25/2025 DEROLD HAUFF
Permit Finaled 4/25/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/10/2024 TREVOR QUAN
Roof/Waste drainage to street Cleared 5/10/2024 TREVOR QUAN
Sewer availability Cleared 5/22/2024 TREVOR QUAN
Construction near power lines Cleared 8/14/2024 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 8/16/2024 CHRISTINA BRACO

Contact Information

Contractor Cgs Home Improvement Inc; Lic. No.: 1037939-B 7189 N FIGUEROA ST      LOS ANGELES, CA 90042
Engineer Nagovitsyn,, Evgeny; Lic. No.: C93527 17436 ARMINTA ST      NORTHRIDGE, CA 91325

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/5/2024 Approved ANTHONY EGSON
PLUMBING-Rough 9/5/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 9/9/2024 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 9/13/2024 Corrections Issued ANTHONY EGSON
Deputy Drilled-In Anchors 9/17/2024 Conditional Approval ANTHONY EGSON
Footing/Foundation/Slab 9/18/2024 Approved ANTHONY EGSON
Rough-Elec/Plmb/HVAC 10/22/2024 Partial Inspection CRAIG DAVIS
Sewer 10/22/2024 Approved CRAIG DAVIS
BUILDING-Rough-Frame 10/30/2024 Conditional Approval BARRY HACHE
Rough-Elec/Plmb/HVAC 10/30/2024 Approved BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Approved BARRY HACHE
Shower Pan 11/5/2024 Not Ready for Inspection BARRY HACHE
Interior/Exterior Lathing 11/20/2024 Not Ready for Inspection JOSH MEISTER
Shower Pan 11/20/2024 Approved JOSH MEISTER
Insulation 12/3/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 12/3/2024 Approved JOSH MEISTER
Drywall Nailing 1/21/2025 Approved ALEX COLIN
BUILDING-Rough-Frame 3/21/2025 Approved LUIS CASTRO
ELECTRICAL-Final 3/21/2025 Approved LUIS CASTRO
Final 3/21/2025 Corrections Issued LUIS CASTRO
Green Building Final 3/21/2025 Approved LUIS CASTRO
Green Building Rough 3/21/2025 Approved LUIS CASTRO
HVAC-Final 3/21/2025 Approved LUIS CASTRO
PLUMBING-Final 3/21/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Not Required LUIS CASTRO
Smoke Detectors 3/21/2025 Approved LUIS CASTRO
Final 4/23/2025 OK to Issue CofO LUIS CASTRO