6121 S KENISTON AVE 90043
Certificate Information: 6121 S KENISTON AVE 90043
- Application / Permit
- 24014-10000-01541
- Plan Check / Job No.
- B24LA06869
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 375 SF. DETACHED GARAGE WITH 124SF ADDTION TO AN ACCESSORY DELLING UNIT PER ENGINEERED DESIGN (1,200 SF max per Ordinance,LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 11/12/2024
- Issuing Office
- Current Status
- CofO Issued on 8/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | AUNG SOE |
| Corrections Issued | 4/23/2024 | AUNG SOE |
| Building Plans Picked Up | 4/25/2024 | APPLICANT |
| Applicant returned to address corrections | 6/18/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 11/12/2024 | EDWIN MARTINEZ |
| Issued | 11/12/2024 | APPLICANT |
| CofO in Progress | 8/6/2025 | MICHAEL LEWIS |
| CofO in Progress | 8/6/2025 | MICHAEL LEWIS |
| CofO in Progress | 8/6/2025 | MICHAEL LEWIS |
| CofO in Progress | 8/11/2025 | WAYNE REGESTER |
| Permit Finaled | 8/12/2025 | DEROLD HAUFF |
| CofO Issued | 8/12/2025 | DEROLD HAUFF |
| Permit Finaled | 8/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/29/2024 | CHRISTINA BRACO |
| Roof/Waste drainage to street | Cleared | 5/29/2024 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 6/11/2024 | CHRISTINA BRACO |
| Grading Pre-Inspection | Cleared | 8/21/2024 | ALEXANDER HELFER |
| Construction near power lines | Cleared | 11/12/2024 | JOSHUA MARTIN |
Contact Information
| Contractor | My Home Builders Inc; Lic. No.: 1002927-B | 20720 VENTURA BLVD 280 WOODLAND HILLS, CA 91364 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/13/2024 | Corrections Issued | AMIR NAZARIAN |
| PLUMBING-Rough | 1/17/2025 | Approved | BARRY HACHE |
| Footing/Foundation/Slab | 2/10/2025 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2025 | Approved | NICHOLAS LOPEZ |
| Wood Frame | 2/25/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 3/17/2025 | Not Ready for Inspection | JOSE MACIAS |
| Green Building Rough | 3/17/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 3/17/2025 | Approved | JOSE MACIAS |
| Rough-Elec/Plmb/HVAC | 3/17/2025 | Corrections Issued | JOSE MACIAS |
| BUILDING-Rough-Frame | 3/21/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 3/21/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Rough | 3/21/2025 | Approved | BARRY HACHE |
| BUILDING-Rough-Frame | 3/24/2025 | Approved | JOSE MACIAS |
| Green Building Rough | 3/24/2025 | Approved | JOSE MACIAS |
| HVAC-Rough | 3/24/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 3/26/2025 | Approved | JOSE MACIAS |
| Insulation | 3/26/2025 | Approved | JOSE MACIAS |
| Drywall Nailing | 4/1/2025 | Approved | WAYNE REGESTER |
| HVAC-Rough | 4/11/2025 | Approved | WAYNE REGESTER |
| Sewer | 4/11/2025 | Corrections Issued | JOSE MACIAS |
| Underground Mechanical | 4/11/2025 | Corrections Issued | JOSE MACIAS |
| HVAC-Rough | 4/21/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Sewer | 4/21/2025 | Approved | WAYNE REGESTER |
| Final | 7/11/2025 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 7/11/2025 | Approved | MICHAEL LEWIS |
| Green Building Final | 7/11/2025 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 7/11/2025 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 7/11/2025 | Approved | MICHAEL LEWIS |
| Final | 7/29/2025 | Not Ready for Inspection | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 7/29/2025 | SGSOV Not Ready | WAYNE REGESTER |
| Final | 8/1/2025 | Corrections Issued | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 8/1/2025 | SGSOV Approved | WAYNE REGESTER |
| Final | 8/5/2025 | Corrections Issued | MICHAEL LEWIS |
| Final | 8/7/2025 | OK to Issue CofO | WAYNE REGESTER |