830 S WINDSOR BLVD 90005

Certificate Information: 830 S WINDSOR BLVD 90005

Application / Permit
24014-10000-01533
Plan Check / Job No.
B24LA06849
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Second story addition and remodel to existing two story single family dwelling.
Permit Issued
Issued on 6/10/2024
Issuing Office
Current Status
CofO Issued on 5/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2024 APPLICANT
Assigned to Plan Check Engineer 4/18/2024 CARLOS MONTES
Corrections Issued 4/23/2024 CARLOS MONTES
Quality Review Completed 4/24/2024 GARO TELMI
Applicant returned to address corrections 5/16/2024 CARLOS MONTES
Plan Check Approved 6/7/2024 CARLOS MONTES
Issued 6/10/2024 APPLICANT
CofO in Progress 4/25/2025 SCOTT FINNILA
Permit Finaled 5/1/2025 DEROLD HAUFF
CofO Issued 5/1/2025 DEROLD HAUFF
Permit Finaled 5/1/2025 DEROLD HAUFF

Permit Application Clearance Information

Miscellaneous Cleared 4/22/2024 RUBEN VASQUEZ
Roof/Waste drainage to street Cleared 5/4/2024 CELINA MORENO
Sewer availability Cleared 5/4/2024 CELINA MORENO
"Q" conditions Cleared 5/14/2024 RUBEN VASQUEZ
HPOZ Cleared 5/16/2024 SUKI GERSHENHORN
Miscellaneous Cleared 5/16/2024 SUKI GERSHENHORN
Eng Process Fee Ord 176,300 Cleared 5/28/2024 DAVID LOPEZ

Contact Information

Contractor Castillo'S Building & Remodeling Inc; Lic. No.: 1087447-B       ,
Engineer Simonian,, Ara; Lic. No.: C37208 314 E BROADWAY STE A      GLENDALE, CA 91205

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/25/2024 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 6/28/2024 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/28/2024 Approved JOAQUIN GREENOUGH
METHANE-Barrier 6/28/2024 Approved JOAQUIN GREENOUGH
METHANE-Subgrade 6/28/2024 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Corrections Issued JEFFREY MEAD
ELECTRICAL-Rough 7/26/2024 Approved ARTHUR NEGRETE
Floor/Roof Diaphrgm/Shear Wall 7/26/2024 Approved ARTHUR NEGRETE
HVAC-Rough 7/26/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 7/26/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 8/8/2024 Partial Inspection JEFFREY MEAD
Shower Pan 8/8/2024 Approved JEFFREY MEAD
Interior/Exterior Lathing 8/9/2024 Partial Approval JEFFREY MEAD
Drywall Nailing 8/21/2024 Not Ready for Inspection JEFFREY MEAD
Insulation 8/21/2024 Corrections Issued JEFFREY MEAD
Drywall Nailing 8/22/2024 Approved JEFFREY MEAD
Insulation 8/22/2024 Approved JEFFREY MEAD
Interior/Exterior Lathing 10/3/2024 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 2/21/2025 Approved JEFFREY MEAD
Final 2/21/2025 Corrections Issued JEFFREY MEAD
Green Building Final 2/21/2025 Approved JEFFREY MEAD
Green Building Rough 2/21/2025 Approved JEFFREY MEAD
METHANE-Final 2/21/2025 Approved JEFFREY MEAD
METHANE-Rough 2/21/2025 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 2/21/2025 SGSOV Approved JEFFREY MEAD
Smoke Detectors 2/21/2025 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Final 4/24/2025 Approved SCOTT FINNILA
Final 4/24/2025 OK to Issue CofO SCOTT FINNILA
Green Building Final 4/24/2025 Approved SCOTT FINNILA
HVAC-Final 4/24/2025 Approved SCOTT FINNILA
PLUMBING-Final 4/24/2025 Approved SCOTT FINNILA
Smoke Detectors 4/24/2025 Approved SCOTT FINNILA