4415 E CATALPA ST 90032
Certificate Information: 4415 E CATALPA ST 90032
- Application / Permit
- 24014-10000-01524
- Plan Check / Job No.
- B24LA06815
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Convert existing detached garage with addition to detached ADU per engineer design. PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 5/8/2024
- Issuing Office
- Current Status
- CofO Issued on 10/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2024 | ALFREDO JARA |
| Corrections Issued | 4/18/2024 | ALFREDO JARA |
| Applicant returned to address corrections | 5/4/2024 | ALFREDO JARA |
| Plan Check Approved | 5/7/2024 | ALFREDO JARA |
| Issued | 5/8/2024 | APPLICANT |
| CofO in Progress | 10/11/2024 | LILIANA PORTILLO |
| Permit Finaled | 10/25/2024 | RUBEN SALAS |
| CofO Issued | 10/25/2024 | RUBEN SALAS |
| Permit Finaled | 10/25/2024 | RUBEN SALAS |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 4/22/2024 | ALFREDO JARA |
| Address approval | Cleared | 4/29/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 4/29/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 4/29/2024 | DAVID LOPEZ |
Contact Information
| Contractor | De La Rosa Construction; Lic. No.: 855010-B | , |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/11/2024 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 6/20/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 6/20/2024 | Partial Approval | LILIANA PORTILLO |
| Sewer | 6/20/2024 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/7/2024 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 8/7/2024 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 8/7/2024 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/12/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/12/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 8/12/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 8/12/2024 | Approved | LILIANA PORTILLO |
| Insulation | 8/15/2024 | Corrections Issued | ANTHONY RAMOS |
| Interior/Exterior Lathing | 8/15/2024 | Partial Approval | ANTHONY RAMOS |
| Insulation | 8/19/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/19/2024 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 8/22/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/3/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 10/3/2024 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Final | 10/3/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 10/3/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/3/2024 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 10/3/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/10/2024 | Approved | LILIANA PORTILLO |
| Final | 10/10/2024 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 10/10/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 10/10/2024 | Approved | LILIANA PORTILLO |