2765 N CARMAR DR 90046

Certificate Information: 2765 N CARMAR DR 90046

Application / Permit
24014-10000-01496
Plan Check / Job No.
B24LA06676
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL AND ADDITION TO (E) SFD WITH GARAGE; EXPAND (E) BEDROOM AND CONVERT CLOSET INTO POWDER ROOM.
Permit Issued
Issued on 8/23/2024
Issuing Office
Metro
Current Status
CofO Issued on 5/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2024 APPLICANT
Assigned to Plan Check Engineer 4/15/2024 LAWRENCE QUIRANTE
Corrections Issued 4/17/2024 LAWRENCE QUIRANTE
Building Plans Picked Up 4/19/2024 APPLICANT
Plan Check Approved 8/22/2024 ALEXANDER JOO
Issued 8/23/2024 APPLICANT
CofO in Progress 5/14/2025 RAUL BARAJAS
Permit Finaled 5/17/2025 DEROLD HAUFF
CofO Issued 5/17/2025 DEROLD HAUFF
Permit Finaled 5/17/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/17/2024 RUSSELL BONVOULOIR
Roof/Waste drainage to street Cleared 4/29/2024 JUSTIN BICOL
Specific Plan Cleared 8/20/2024 JUDE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 8/21/2024 JUSTIN BICOL

Contact Information

Architect Leifield,, Ryan Elizabeth; Lic. No.: C38672 1749 N ALEXANDRIA AVE      LOS ANGELES, CA 90027
Contractor Capriwell Development And Construction; Lic. No.: 1077424-B 301 N LAKE AVE, SUITE 600      PASADENA, CA 91101
Engineer Schwartz,, Eric; Lic. No.: C81191 3451 GRIFFITH PARK BLVD      LOS ANGELES, CA 90027

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/29/2024 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 8/30/2024 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 8/30/2024 Corrections Issued RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 9/4/2024 Approved RAUL BARAJAS
Deputy Drilled-In Anchors 9/13/2024 Conditional Approval RAUL BARAJAS
Structural Steel Frame 9/19/2024 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 10/29/2024 Not Ready for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Partial Inspection RAUL BARAJAS
Green Building Rough 10/29/2024 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 11/8/2024 No Access for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 11/8/2024 No Access for Inspection RAUL BARAJAS
Green Building Rough 11/8/2024 No Access for Inspection RAUL BARAJAS
Structural Steel Frame 11/8/2024 No Access for Inspection RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Approved RAUL BARAJAS
Insulation 11/13/2024 Partial Approval RAUL BARAJAS
Structural Steel Frame 11/13/2024 Approved RAUL BARAJAS
Wood Frame 11/13/2024 Corrections Issued RAUL BARAJAS
Deputy Drilled-In Anchors 11/27/2024 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 12/2/2024 Approved RAUL BARAJAS
Drywall Nailing 12/9/2024 Partial Approval ALEX COLIN
Interior/Exterior Lathing 1/22/2025 Approved RAUL BARAJAS
BUILDING-Rough-Frame 4/16/2025 Approved BRIAN SULLIVAN
Green Building Rough 4/16/2025 Approved BRIAN SULLIVAN
Final 5/2/2025 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 5/2/2025 Approved BRIAN SULLIVAN
Green Building Final 5/2/2025 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 5/2/2025 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 5/2/2025 Approved BRIAN SULLIVAN
Final 5/14/2025 OK to Issue CofO RAUL BARAJAS