756 E 94TH ST 90002
Certificate Information: 756 E 94TH ST 90002
- Application / Permit
- 24014-10000-01492
- Plan Check / Job No.
- B24LA06648
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: ADDITION TO (E) DETACHED GARAGE TO CREATE A (N) IRREGULAR SHAPED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 6/18/2024
- Issuing Office
- Current Status
- CofO Issued on 4/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2024 | ALFRED RAMIREZ |
| Corrections Issued | 4/17/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 5/23/2024 | GURUNATH NESARAJAH |
| Plan Check Approved | 6/10/2024 | GURUNATH NESARAJAH |
| Issued | 6/18/2024 | APPLICANT |
| Permit Finaled | 4/23/2025 | ANSON MAGLASANG |
| CofO Issued | 4/23/2025 | ANSON MAGLASANG |
| Permit Finaled | 4/23/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 4/23/2024 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 4/23/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2024 | CELINA MORENO |
| Sewer availability | Cleared | 5/16/2024 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/30/2024 | Approved | BEN MOLSTAD |
| Excavation/Setback/Form/Re-Bar | 9/30/2024 | No Access for Inspection | BARRY HACHE |
| Underground Mechanical | 9/30/2024 | No Access for Inspection | BARRY HACHE |
| Underground Mechanical | 10/2/2024 | Corrections Issued | BARRY HACHE |
| Excavation/Setback/Form/Re-Bar | 10/7/2024 | Not Ready for Inspection | BARRY HACHE |
| Sewer | 10/7/2024 | Corrections Issued | BARRY HACHE |
| Footing/Foundation/Slab | 10/25/2024 | Corrections Issued | ANTHONY EGSON |
| Sewer | 10/25/2024 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 10/30/2024 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 12/9/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 12/12/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 12/12/2024 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Partial Approval | JOSEPH MCGARRY |
| Underground Mechanical | 12/13/2024 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 12/17/2024 | Conditional Approval | JOSEPH MCGARRY |
| Green Building Rough | 12/17/2024 | Approved | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 12/17/2024 | Approved | JOSEPH MCGARRY |
| Insulation | 12/23/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 12/23/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Insulation | 12/26/2024 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 12/26/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 1/13/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 3/14/2025 | Approved | ANTHONY EGSON |
| Final | 3/14/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/14/2025 | Approved | ANTHONY EGSON |
| Green Building Final | 3/14/2025 | Not Ready for Inspection | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 3/14/2025 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 3/14/2025 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 3/21/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 3/21/2025 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 3/21/2025 | Approved | ANTHONY EGSON |
| HVAC-Final | 3/21/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 3/21/2025 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 3/21/2025 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 3/21/2025 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2025 | No Access for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Final | 3/27/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 3/27/2025 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 3/27/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 3/27/2025 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 3/27/2025 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 3/27/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 3/28/2025 | Approved | ANTHONY EGSON |
| Final | 3/28/2025 | Partial Approval | ANTHONY EGSON |
| Gas Test | 3/28/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 3/28/2025 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 3/28/2025 | SGSOV Approved | ANTHONY EGSON |