1875 1/2 S COCHRAN AVE 90019

Certificate Information: 1875 1/2 S COCHRAN AVE 90019

Application / Permit
24014-10000-01483
Plan Check / Job No.
B24LA06574
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
E-plan. New detached ADU (774 SF, 2-story)over (e) garage. ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
Permit Issued
Issued on 10/11/2024
Issuing Office
Current Status
CofO Issued on 11/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2024 APPLICANT
Assigned to Plan Check Engineer 4/18/2024 SUNMIN LEE
Corrections Issued 4/20/2024 SUNMIN LEE
Quality Review Completed 5/9/2024 GARO TELMI
Applicant returned to address corrections 10/8/2024 SUNMIN LEE
Plan Check Approved 10/10/2024 SUNMIN LEE
Issued 10/11/2024 APPLICANT
CofO in Progress 11/21/2025 ALEJANDRO DE ARTOLA
Permit Finaled 11/23/2025 DEROLD HAUFF
CofO Issued 11/23/2025 DEROLD HAUFF
Permit Finaled 11/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/20/2024 ANTHONY TRAN
Eng Process Fee Ord 176,300 Cleared 6/20/2024 ADRIAN SANCHEZ
Sewer availability Cleared 6/20/2024 ADRIAN SANCHEZ
Construction within easement Cleared 8/3/2024 RIDWAN HARDY
Address approval Cleared 8/29/2024 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Hwang,, Junho; Lic. No.: NA5592       ,
Engineer Hwang,, Junho; Lic. No.: S5592 2450 W MAIN ST      ALHAMBRA, CA 91801
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/12/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 2/26/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 2/26/2025 Partial Inspection ALEX COLIN
Footing/Foundation/Slab 2/27/2025 Approved ARTHUR NEGRETE
Deputy Drilled-In Anchors 2/28/2025 Conditional Approval ALEX COLIN
Floor/Roof Diaphrgm/Shear Wall 3/10/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 3/10/2025 Partial Inspection ALEX COLIN
Floor/Roof Diaphrgm/Shear Wall 3/29/2025 Approved LUIS CASTRO
Wood Frame 3/29/2025 Not Ready for Inspection LUIS CASTRO
HVAC-Rough 4/7/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 4/16/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 4/16/2025 Approved ARTHUR NEGRETE
Insulation 4/22/2025 Not Ready for Inspection ALEX COLIN
BUILDING-Rough-Frame 4/24/2025 Approved ARTHUR NEGRETE
Green Building Rough 4/24/2025 Approved ARTHUR NEGRETE
Insulation 4/24/2025 Approved ARTHUR NEGRETE
Shower Pan 4/24/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 4/29/2025 Approved ARTHUR NEGRETE
Drywall Nailing 5/5/2025 Approved ALEX COLIN
Service/Power Release 7/25/2025 Approved ARTHUR NEGRETE
Final 8/29/2025 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 8/29/2025 Conditional Approval ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 8/29/2025 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 8/29/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Final 9/2/2025 Approved ARTHUR NEGRETE
HVAC-Final 9/2/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 9/2/2025 Approved ARTHUR NEGRETE
Final 11/21/2025 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 11/21/2025 Approved ALEJANDRO DE ARTOLA