1875 1/2 S COCHRAN AVE 90019
Certificate Information: 1875 1/2 S COCHRAN AVE 90019
- Application / Permit
- 24014-10000-01483
- Plan Check / Job No.
- B24LA06574
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- E-plan. New detached ADU (774 SF, 2-story)over (e) garage. ADU CHECKED PER LAMC 12.22 A.33 (C)-(D)
- Permit Issued
- Issued on 10/11/2024
- Issuing Office
- Current Status
- CofO Issued on 11/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | SUNMIN LEE |
| Corrections Issued | 4/20/2024 | SUNMIN LEE |
| Quality Review Completed | 5/9/2024 | GARO TELMI |
| Applicant returned to address corrections | 10/8/2024 | SUNMIN LEE |
| Plan Check Approved | 10/10/2024 | SUNMIN LEE |
| Issued | 10/11/2024 | APPLICANT |
| CofO in Progress | 11/21/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 11/23/2025 | DEROLD HAUFF |
| CofO Issued | 11/23/2025 | DEROLD HAUFF |
| Permit Finaled | 11/23/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/20/2024 | ANTHONY TRAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/20/2024 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 6/20/2024 | ADRIAN SANCHEZ |
| Construction within easement | Cleared | 8/3/2024 | RIDWAN HARDY |
| Address approval | Cleared | 8/29/2024 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hwang,, Junho; Lic. No.: NA5592 | , |
| Engineer | Hwang,, Junho; Lic. No.: S5592 | 2450 W MAIN ST ALHAMBRA, CA 91801 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/12/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 2/26/2025 | Approved | ARTHUR NEGRETE |
| Special/Order Compliance | 2/26/2025 | Partial Inspection | ALEX COLIN |
| Footing/Foundation/Slab | 2/27/2025 | Approved | ARTHUR NEGRETE |
| Deputy Drilled-In Anchors | 2/28/2025 | Conditional Approval | ALEX COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2025 | Approved | ARTHUR NEGRETE |
| Special/Order Compliance | 3/10/2025 | Partial Inspection | ALEX COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2025 | Approved | LUIS CASTRO |
| Wood Frame | 3/29/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 4/7/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 4/16/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 4/16/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 4/22/2025 | Not Ready for Inspection | ALEX COLIN |
| BUILDING-Rough-Frame | 4/24/2025 | Approved | ARTHUR NEGRETE |
| Green Building Rough | 4/24/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 4/24/2025 | Approved | ARTHUR NEGRETE |
| Shower Pan | 4/24/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 4/29/2025 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 5/5/2025 | Approved | ALEX COLIN |
| Service/Power Release | 7/25/2025 | Approved | ARTHUR NEGRETE |
| Final | 8/29/2025 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 8/29/2025 | Conditional Approval | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 8/29/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 9/2/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 9/2/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 9/2/2025 | Approved | ARTHUR NEGRETE |
| Final | 11/21/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 11/21/2025 | Approved | ALEJANDRO DE ARTOLA |