10456 W HOLMAN AVE 90024
Certificate Information: 10456 W HOLMAN AVE 90024
- Application / Permit
- 24014-10000-01463
- Plan Check / Job No.
- B24LA06506
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Addition and alteration of existing Single Family Dwelling. Remove (E) porte cochere and (E) covered porch, Addition of new front cover porch entry (37.88 SF), and new Foyer (94.75 SF)
- Permit Issued
- Issued on 5/9/2024
- Issuing Office
- Current Status
- CofO Issued on 10/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2024 | MINA HABILI |
| Corrections Issued | 4/16/2024 | MINA HABILI |
| Applicant returned to address corrections | 5/2/2024 | JOSEPH RAFOLS |
| Plan Check Approved | 5/8/2024 | JOSEPH RAFOLS |
| Issued | 5/9/2024 | APPLICANT |
| CofO in Progress | 10/10/2025 | DANIEL VERA |
| Permit Finaled | 10/14/2025 | RICHARD STEINBACH |
| CofO Issued | 10/14/2025 | RICHARD STEINBACH |
| Permit Finaled | 10/14/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/18/2024 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2024 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 4/23/2024 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 4/25/2024 | FREDDY GARCIA |
| Miscellaneous | Cleared | 5/3/2024 | MINA HABILI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baich,, Brendon Chad; Lic. No.: C83347 | PO BOX 8840 POMONA, CA 91701 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/22/2024 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 5/22/2024 | Approved | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 5/28/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2024 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2024 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 6/3/2024 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 6/24/2024 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 6/28/2024 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 6/28/2024 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 6/28/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 7/1/2024 | Partial Approval | MEL KHACHATOURIAN |
| Drywall Nailing | 7/5/2024 | Approved | SEAN HAUPT |
| Pre-Inspection | 8/5/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 8/8/2024 | Approved | STEPHANIE SWANSON |
| Final | 8/30/2024 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 8/30/2024 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 8/30/2024 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 8/30/2024 | Approved | SEAN HAUPT |
| Final | 10/8/2025 | OK to Issue CofO | DANIEL VERA |