809-809 1/2 W 80TH ST 90044
Certificate Information: 809-809 1/2 W 80TH ST 90044
- Application / Permit
- 24014-10000-01456
- Plan Check / Job No.
- B24LA06451
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE WITH ADDITION INTO TWO DETACHED ACCESSORY DWELLING UNITS PER CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g) (1-STORY)
- Permit Issued
- Issued on 11/6/2024
- Issuing Office
- Metro
- Current Status
- Issued on 11/6/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/9/2024 | APPLICANT |
| Assigned to Zoning Architect | 4/17/2024 | NICOLE SALEEBA |
| Assigned to Plan Check Engineer | 4/18/2024 | CARLOS MONTES |
| Corrections Issued | 4/22/2024 | CARLOS MONTES |
| Quality Review Completed | 4/24/2024 | KEN GILL |
| Building Plans Picked Up | 5/2/2024 | APPLICANT |
| Applicant returned to address corrections | 11/4/2024 | CARLOS MONTES |
| Plan Check Approved | 11/6/2024 | CARLOS MONTES |
| Issued | 11/6/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/17/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 5/22/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 5/22/2024 | DAVID LOPEZ |
| Zoning Plan Check | Cleared | 7/9/2024 | NICOLE SALEEBA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/5/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 6/5/2025 | Corrections Issued | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 6/9/2025 | Corrections Issued | WAYNE REGESTER |
| Excavation/Setback/Form/Re-Bar | 6/11/2025 | Partial Approval | JOSE MACIAS |
| Underground Mechanical | 6/11/2025 | Approved | JOSE MACIAS |
| Sewer | 8/8/2025 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 8/8/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 3/13/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 3/13/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Rough | 3/13/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 4/2/2026 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 5/13/2026 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 5/18/2026 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 5/18/2026 | Corrections Issued | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 6/5/2026 | No Result Entered | JOHN QUINTANILLA |
| Green Building Rough | 6/5/2026 | No Result Entered | JOHN QUINTANILLA |
| PLUMBING-Rough | 6/5/2026 | No Result Entered | JOHN QUINTANILLA |