8328 S AIRLANE AVE 90045
Certificate Information: 8328 S AIRLANE AVE 90045
- Application / Permit
- 24014-10000-01433
- Plan Check / Job No.
- B24LA06346
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New A.D.U. addition to existing detached garage per Ordinance (LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 2/2/2025
- Issuing Office
- Current Status
- Issued on 2/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2024 | CAROLEAN BASMA |
| Corrections Issued | 4/12/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 10/1/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 1/3/2025 | DAVID CASTILLO |
| Applicant returned to address corrections | 1/8/2025 | HOOMAN HAJIZADEH |
| Plan Check Approved | 1/13/2025 | HOOMAN HAJIZADEH |
| Issued | 2/2/2025 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 8/26/2024 | RIDWAN HARDY |
| Address approval | Cleared | 9/15/2024 | DIANA RENTERIA |
| Specific Plan | Cleared | 11/12/2024 | FREDDY GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2024 | LIAM ODONOVAN |
| Sewer availability | Cleared | 12/20/2024 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 12/26/2024 | ANTHONY MAINEZ |
Contact Information
| Architect | Khaleeli,, Bizhan; Lic. No.: C29971 | 2025 PASEO DEL SOL PALOS VERDES ESTATES, CA 90274 |
| Contractor | Precision General Construction Inc; Lic. No.: 1030555-B | , |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/10/2025 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 2/10/2025 | Partial Approval | TEMISTOCLES CAAL |
| Sewer | 2/10/2025 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 2/20/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 4/3/2025 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 4/3/2025 | Approved | JESUS PINEDA |
| Deputy Wood Construction | 4/4/2025 | Conditional Approval | MICHAEL PELHAM |
| HVAC-Rough | 4/10/2025 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 4/21/2025 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 4/21/2025 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 4/29/2025 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 4/29/2025 | Partial Approval | BOBBY KEY |
| Insulation | 5/6/2025 | Corrections Issued | JESUS PINEDA |
| Underground Mechanical | 5/6/2025 | Approved | JESUS PINEDA |
| Insulation | 5/8/2025 | Approved | JESUS PINEDA |
| Drywall Nailing | 5/16/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 5/16/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 8/1/2025 | Corrections Issued | RUBEN RIVAS |
| Gas Test | 8/1/2025 | Corrections Issued | RUBEN RIVAS |
| Rough-Elec/Plmb/HVAC | 8/1/2025 | Partial Approval | RUBEN RIVAS |
| Gas Test | 8/14/2025 | Approved | JESUS PINEDA |
| Underground Mechanical | 8/14/2025 | Approved | JESUS PINEDA |