2921 S GENESEE AVE 90016

Certificate Information: 2921 S GENESEE AVE 90016

Application / Permit
24014-10000-01415
Plan Check / Job No.
B24LA06273
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Convert (E) Garage into an Accessory Dwelling Unit with an addition per LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 2/7/2025
Issuing Office
Current Status
CofO Corrected on 1/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/8/2024 APPLICANT
Assigned to Plan Check Engineer 4/10/2024 AMY GUEVARRA
Corrections Issued 4/12/2024 AMY GUEVARRA
Applicant returned to address corrections 1/23/2025 AMY GUEVARRA
Plan Check Approved 2/7/2025 AMY GUEVARRA
Issued 2/7/2025 APPLICANT
CofO in Progress 7/24/2025 ARTHUR NEGRETE
CofO Issued-Status Void 7/27/2025 DEROLD HAUFF
Permit Finaled-Status Void 7/27/2025 DEROLD HAUFF
Intent to Revoke-Status Void 8/19/2025 SHAHEN AKELYAN
Re-Activate Permit 8/26/2025 SHAHEN AKELYAN
Re-Activate Permit 8/26/2025 DEROLD HAUFF
CofO in Progress 8/27/2025 DEROLD HAUFF
No Progress 9/13/2025 DEROLD HAUFF
CofO in Progress 11/14/2025 OSVALDO PARAMO
CofO in Progress 11/20/2025 ARTHUR NEGRETE
CofO in Progress 11/21/2025 DEROLD HAUFF
No Progress 11/21/2025 DEROLD HAUFF
CofO in Progress 1/13/2026 DANIEL ORRANTE
CofO in Progress 1/19/2026 DANIEL ORRANTE
Permit Finaled 1/19/2026 DANIEL ORRANTE
CofO Corrected 1/19/2026 DANIEL ORRANTE
Permit Finaled 1/19/2026 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/17/2024 CHRISTINA BRACO
Roof/Waste drainage to street Cleared 4/17/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 4/19/2024 CHRISTINA BRACO
Sewer availability Cleared 4/19/2024 CHRISTINA BRACO
Flood clearance Cleared 1/16/2025 TUYEN LE

Contact Information

Contractor Owner-Builder       ,
Engineer Crook,, Barrett Cameron; Lic. No.: C57196 5306 MULHOLLAND DRIVE      SUMMERVILLE, SC 29485

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/26/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 2/26/2025 Not Ready for Inspection ARTHUR NEGRETE
Special/Order Compliance 2/26/2025 Partial Inspection ALEX COLIN
Underground Mechanical 2/26/2025 Approved ARTHUR NEGRETE
Deputy Wood Construction 3/27/2025 Conditional Approval ALEX COLIN
ELECTRICAL-Rough 3/27/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 3/27/2025 Approved ARTHUR NEGRETE
Wood Frame 3/27/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 4/10/2025 Partial Approval ARTHUR NEGRETE
HVAC-Rough 4/10/2025 Approved ARTHUR NEGRETE
Insulation 4/10/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 4/10/2025 Approved ARTHUR NEGRETE
Drywall Nailing 4/16/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 4/16/2025 Approved ARTHUR NEGRETE
Gas Test 4/16/2025 Approved ARTHUR NEGRETE
Underground Mechanical 4/16/2025 Approved ARTHUR NEGRETE
Sewer 5/19/2025 Approved REGINA MENDEZ
BUILDING-Rough-Frame 6/10/2025 Partial Approval ARTHUR NEGRETE
FLOOD-Proofing Certificate 6/10/2025 Not Ready for Inspection ARTHUR NEGRETE
Final 6/10/2025 Corrections Issued ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 6/10/2025 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 6/10/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 7/24/2025 Approved ARTHUR NEGRETE
FLOOD-Proofing Certificate 7/24/2025 Approved ARTHUR NEGRETE
Final 7/24/2025 Conditional Approval ARTHUR NEGRETE
Service/Power Release 11/14/2025 Approved OSVALDO PARAMO
Final 11/20/2025 OK to Issue CofO ARTHUR NEGRETE