817-819 1/2 W 64TH ST 90044
Certificate Information: 817-819 1/2 W 64TH ST 90044
- Application / Permit
- 24014-10000-01383
- Plan Check / Job No.
- B24LA06181
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert existing 1st story garage attached to single family dwelling to ADU plus addition to ADU. (CONVERSION: 757 SQ. FT. / ADDITION: 9 SQ. FT. / TOTAL: 766 SQ. FT.). PER LAMC 12.22 A.33(c) AND (e)
- Permit Issued
- Issued on 1/16/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2024 | NGHI SU |
| Corrections Issued | 4/9/2024 | NGHI SU |
| Building Plans Picked Up | 4/26/2024 | APPLICANT |
| Plan Check Approved | 9/20/2024 | DANIEL SMILEY |
| Issued | 1/16/2025 | APPLICANT |
| CofO in Progress | 8/21/2025 | BARRY HACHE |
| Permit Finaled | 8/24/2025 | DEROLD HAUFF |
| CofO Issued | 8/24/2025 | DEROLD HAUFF |
| Permit Finaled | 8/24/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 4/29/2024 | RICARDO BOHORQUEZ |
| Address approval | Cleared | 5/8/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2024 | WALLIE JONG |
| Sewer availability | Cleared | 5/13/2024 | WALLIE JONG |
| Construction near power lines | Cleared | 9/10/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Sarmiento Construction; Lic. No.: 819153-B | 13012 WELBY WAY NORTH HOLLYWOOD, CA 91606 |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/18/2025 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 2/21/2025 | Approved | LUIS CASTRO |
| Underground Mechanical | 4/2/2025 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 4/9/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Rough | 4/9/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 4/14/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 4/14/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Rough | 4/16/2025 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2025 | Partial Inspection | BARRY HACHE |
| PLUMBING-Rough | 4/16/2025 | Approved | BARRY HACHE |
| HVAC-Rough | 4/24/2025 | Approved | WAYNE REGESTER |
| Interior/Exterior Lathing | 4/24/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 4/30/2025 | Approved | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2025 | Approved | BARRY HACHE |
| Green Building Rough | 4/30/2025 | Approved | BARRY HACHE |
| Insulation | 5/5/2025 | Approved | ANTHONY RAMOS |
| Shower Pan | 5/5/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 5/8/2025 | Approved | BARRY HACHE |
| Final | 7/31/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 8/6/2025 | Not Ready for Inspection | BARRY HACHE |
| Final | 8/6/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 8/15/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 8/15/2025 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 8/15/2025 | SGSOV Approved | BARRY HACHE |
| Smoke Detectors | 8/15/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 8/19/2025 | Approved | BARRY HACHE |
| Green Building Final | 8/19/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 8/19/2025 | Corrections Issued | BARRY HACHE |
| Final | 8/20/2025 | Conditional Approval | BARRY HACHE |
| Green Building Final | 8/20/2025 | Approved | BARRY HACHE |
| HVAC-Final | 8/20/2025 | Approved | BARRY HACHE |
| Final | 8/21/2025 | OK to Issue CofO | BARRY HACHE |