430 W CENTURY BLVD 90003

Certificate Information: 430 W CENTURY BLVD 90003

Application / Permit
24014-10000-01372
Plan Check / Job No.
B24LA06128
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
20'-0" X 40'-5" IRREGULAR SHAPED ADDITION AND CONVERT DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) - PER ENGINEER
Permit Issued
Issued on 11/19/2024
Issuing Office
Current Status
Issued on 11/19/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/8/2024 APPLICANT
Assigned to Plan Check Engineer 4/12/2024 DANIEL ABRAMYAN
Corrections Issued 4/15/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 8/15/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 10/4/2024 DANIEL ABRAMYAN
Plan Check Approved 11/18/2024 DANIEL ABRAMYAN
Issued 11/19/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/23/2024 TREVOR QUAN
Roof/Waste drainage to street Cleared 7/23/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 8/13/2024 JUSTIN BICOL
Sewer availability Cleared 8/13/2024 JUSTIN BICOL
Construction near power lines Cleared 10/17/2024 EDGAR PASCUA

Contact Information

Contractor Kinslow K W Construction Inc; Lic. No.: 799861-B       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 2999 OVERLAND AVE STE 103      LOS ANGELES, CA 90064

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/6/2024 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 12/11/2024 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 12/18/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 12/18/2024 Partial Approval ANTHONY EGSON
Deputy Wood Construction 1/22/2025 Conditional Approval ANSON MAGLASANG
BUILDING-Rough-Frame 1/24/2025 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 1/24/2025 Corrections Issued BEN MOLSTAD
Green Building Rough 1/24/2025 Not Ready for Inspection BEN MOLSTAD
MERV13>=Rough 1/24/2025 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 1/24/2025 Corrections Issued BEN MOLSTAD
BUILDING-Rough-Frame 2/3/2025 Partial Approval BEN MOLSTAD
ELECTRICAL-Rough 2/3/2025 Approved BEN MOLSTAD
Green Building Rough 2/3/2025 Approved BEN MOLSTAD
MERV13>=Rough 2/3/2025 Approved BEN MOLSTAD
PLUMBING-Rough 2/3/2025 Approved BEN MOLSTAD
Insulation 2/10/2025 Approved BEN MOLSTAD
Interior/Exterior Lathing 2/10/2025 Partial Approval BEN MOLSTAD
Drywall Nailing 3/14/2025 Approved BEN MOLSTAD
BUILDING-Rough-Frame 5/29/2025 Approved BEN MOLSTAD
ELECTRICAL-Final 5/29/2025 Corrections Issued BEN MOLSTAD
Final 5/29/2025 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 5/29/2025 Approved BEN MOLSTAD
Green Building Final 5/29/2025 Not Ready for Inspection BEN MOLSTAD
MERV13>=Final 5/29/2025 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 5/29/2025 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 5/29/2025 Approved BEN MOLSTAD
Final 6/4/2025 Corrections Issued BEN MOLSTAD
Green Building Final 6/4/2025 Not Ready for Inspection BEN MOLSTAD
MERV13>=Final 6/4/2025 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 6/4/2025 SGSOV Not Ready BEN MOLSTAD
Final 10/29/2025 Corrections Issued BEN MOLSTAD
Green Building Final 10/29/2025 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV Approved BEN MOLSTAD
Final 12/18/2025 Corrections Issued BEN MOLSTAD
ELECTRICAL-Final 1/21/2026 Corrections Issued BEN MOLSTAD
ELECTRICAL-Final 1/28/2026 Approved ARTHUR NEGRETE