3962 1/2 W SENECA AVE 90039
Certificate Information: 3962 1/2 W SENECA AVE 90039
- Application / Permit
- 24014-10000-01354
- Plan Check / Job No.
- B24LA06077
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. 2-story ADU attached to existing 2-car garage PER GCS 65852.2(e) (1)(B) and LAMC 12.22a.33(c),(d) and (g)
- Permit Issued
- Issued on 1/31/2025
- Issuing Office
- Current Status
- CofO Issued on 7/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 4/26/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 5/1/2024 | GARO TELMI |
| Applicant returned to address corrections | 7/31/2024 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 1/9/2025 | MARCELA FRANQUEZ |
| Plan Check Approved | 1/31/2025 | MARCELA FRANQUEZ |
| Issued | 1/31/2025 | APPLICANT |
| CofO in Progress | 7/25/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 7/27/2025 | DEROLD HAUFF |
| CofO Issued | 7/27/2025 | DEROLD HAUFF |
| Permit Finaled | 7/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 6/21/2024 | JAZMIN ROQUE |
| Address approval | Cleared | 6/25/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 6/26/2024 | JESSICA OPINION |
| Tenant Habitability Plan | Cleared | 6/27/2024 | RICARDO BOHORQUEZ |
| Roof/Waste drainage to street | Cleared | 7/25/2024 | JESSICA OPINION |
Contact Information
| Contractor | Mariano Development Inc; Lic. No.: 982720-B | , |
| Engineer | Hernandez,, Gerardo; Lic. No.: C78115 | 1426 E STUART AVE WEST COVINA, CA 91791 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/18/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 2/26/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 3/14/2025 | Approved | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 3/14/2025 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 4/29/2025 | Approved | NICHOLAS LOPEZ |
| HVAC-Rough | 4/29/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Rough | 4/29/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Sewer | 4/29/2025 | Approved | NICHOLAS LOPEZ |
| Underground Mechanical | 4/29/2025 | Partial Approval | NICHOLAS LOPEZ |
| BUILDING-Rough-Frame | 5/2/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 5/2/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 5/2/2025 | Partial Approval | NICHOLAS LOPEZ |
| Shower Pan | 5/2/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 5/7/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 5/7/2025 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 5/16/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 5/16/2025 | Approved | REGINA MENDEZ |
| ELECTRICAL-Final | 6/25/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Final | 6/25/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 6/25/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 6/25/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 6/25/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 7/23/2025 | Approved | NICHOLAS LOPEZ |
| Final | 7/23/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| Green Building Final | 7/23/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 7/23/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/23/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| Service/Power Release | 7/23/2025 | Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 7/23/2025 | Approved | NICHOLAS LOPEZ |