3962 1/2 W SENECA AVE 90039

Certificate Information: 3962 1/2 W SENECA AVE 90039

Application / Permit
24014-10000-01354
Plan Check / Job No.
B24LA06077
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. 2-story ADU attached to existing 2-car garage PER GCS 65852.2(e) (1)(B) and LAMC 12.22a.33(c),(d) and (g)
Permit Issued
Issued on 1/31/2025
Issuing Office
Current Status
CofO Issued on 7/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/4/2024 APPLICANT
Assigned to Plan Check Engineer 4/18/2024 MARCELA FRANQUEZ
Corrections Issued 4/26/2024 MARCELA FRANQUEZ
Quality Review Completed 5/1/2024 GARO TELMI
Applicant returned to address corrections 7/31/2024 MARCELA FRANQUEZ
Applicant returned to address corrections 1/9/2025 MARCELA FRANQUEZ
Plan Check Approved 1/31/2025 MARCELA FRANQUEZ
Issued 1/31/2025 APPLICANT
CofO in Progress 7/25/2025 NICHOLAS LOPEZ
Permit Finaled 7/27/2025 DEROLD HAUFF
CofO Issued 7/27/2025 DEROLD HAUFF
Permit Finaled 7/27/2025 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 6/21/2024 JAZMIN ROQUE
Address approval Cleared 6/25/2024 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 6/26/2024 JESSICA OPINION
Sewer availability Cleared 6/26/2024 JESSICA OPINION
Tenant Habitability Plan Cleared 6/27/2024 RICARDO BOHORQUEZ
Roof/Waste drainage to street Cleared 7/25/2024 JESSICA OPINION

Contact Information

Contractor Mariano Development Inc; Lic. No.: 982720-B       ,
Engineer Hernandez,, Gerardo; Lic. No.: C78115 1426 E STUART AVE      WEST COVINA, CA 91791

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/18/2025 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 2/26/2025 Corrections Issued NICHOLAS LOPEZ
Excavation/Setback/Form/Re-Bar 3/14/2025 Approved NICHOLAS LOPEZ
Footing/Foundation/Slab 3/14/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 4/29/2025 Approved NICHOLAS LOPEZ
HVAC-Rough 4/29/2025 Approved NICHOLAS LOPEZ
PLUMBING-Rough 4/29/2025 Conditional Approval NICHOLAS LOPEZ
Sewer 4/29/2025 Approved NICHOLAS LOPEZ
Underground Mechanical 4/29/2025 Partial Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 5/2/2025 Approved NICHOLAS LOPEZ
Green Building Rough 5/2/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 5/2/2025 Partial Approval NICHOLAS LOPEZ
Shower Pan 5/2/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 5/7/2025 Approved NICHOLAS LOPEZ
Insulation 5/7/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 5/16/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 5/16/2025 Approved REGINA MENDEZ
ELECTRICAL-Final 6/25/2025 Corrections Issued ALIZAH MAYAGOITIA
Final 6/25/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 6/25/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 6/25/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 6/25/2025 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Final 7/23/2025 Approved NICHOLAS LOPEZ
Final 7/23/2025 OK to Issue CofO NICHOLAS LOPEZ
Green Building Final 7/23/2025 Approved NICHOLAS LOPEZ
PLUMBING-Final 7/23/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 7/23/2025 SGSOV Approved NICHOLAS LOPEZ
Service/Power Release 7/23/2025 Approved NICHOLAS LOPEZ
Smoke Detectors 7/23/2025 Approved NICHOLAS LOPEZ