1923 W 76TH ST 90047

Certificate Information: 1923 W 76TH ST 90047

Application / Permit
24014-10000-01331
Plan Check / Job No.
B24LA06021
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Addition (250 SF) to (E) SFD at the rear of the structure.
Permit Issued
Issued on 5/15/2024
Issuing Office
Current Status
CofO Issued on 3/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2024 APPLICANT
Assigned to Plan Check Engineer 4/9/2024 GEORGE ALVAREZ
Corrections Issued 4/10/2024 GEORGE ALVAREZ
Plan Check Approved 5/14/2024 ZAW HAN
Issued 5/15/2024 APPLICANT
CofO in Progress 2/26/2025 NICHOLAS LOPEZ
Permit Finaled 3/2/2025 DEROLD HAUFF
CofO Issued 3/2/2025 DEROLD HAUFF
Permit Finaled 3/2/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/17/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 5/9/2024 CHRISTINA BRACO
Sewer availability Cleared 5/9/2024 CHRISTINA BRACO

Contact Information

Contractor Gt Remodeling Inc; Lic. No.: 1091310-B       ,
Engineer Crook,, Barrett Cameron; Lic. No.: C57196 5306 MULHOLLAND DRIVE      SUMMERVILLE, SC 29485

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/10/2024 Conditional Approval JOSE MACIAS
Excavation/Setback/Form/Re-Bar 8/7/2024 Corrections Issued JOSE MACIAS
Excavation/Setback/Form/Re-Bar 8/21/2024 Corrections Issued JOSE MACIAS
Excavation/Setback/Form/Re-Bar 8/30/2024 Approved JOSE MACIAS
Deputy Reinf. Concrete 9/5/2024 No Access for Inspection AMIR NAZARIAN
BUILDING-Rough-Frame 9/12/2024 Corrections Issued AMIR NAZARIAN
PLUMBING-Rough 9/12/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 9/17/2024 Corrections Issued AMIR NAZARIAN
Wood Frame 9/19/2024 Partial Approval AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 9/23/2024 Partial Approval AMIR NAZARIAN
BUILDING-Rough-Frame 10/4/2024 Partial Approval LUIS CASTRO
ELECTRICAL-Rough 10/4/2024 Approved LUIS CASTRO
HVAC-Rough 10/4/2024 Approved LUIS CASTRO
BUILDING-Rough-Frame 10/8/2024 Corrections Issued AMIR NAZARIAN
BUILDING-Rough-Frame 10/25/2024 Corrections Issued AMIR NAZARIAN
BUILDING-Rough-Frame 11/4/2024 Corrections Issued AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Corrections Issued AMIR NAZARIAN
Interior/Exterior Lathing 11/12/2024 Corrections Issued AMIR NAZARIAN
Shower Pan 11/12/2024 Approved AMIR NAZARIAN
Insulation 11/15/2024 Conditional Approval ALEX COLIN
Interior/Exterior Lathing 11/15/2024 Corrections Issued ALEX COLIN
Drywall Nailing 12/2/2024 Approved AMIR NAZARIAN
Interior/Exterior Lathing 12/2/2024 Corrections Issued AMIR NAZARIAN
Shower Pan 12/2/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 2/6/2025 Approved JOSE MACIAS
Final 2/6/2025 Corrections Issued JOSE MACIAS
Footing/Foundation/Slab 2/6/2025 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 2/6/2025 SGSOV Not Ready JOSE MACIAS
Smoke Detectors 2/6/2025 Not Ready for Inspection JOSE MACIAS
Final 2/12/2025 No Access for Inspection JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 2/12/2025 SGSOV Not Ready JOSE MACIAS
Smoke Detectors 2/12/2025 No Access for Inspection JOSE MACIAS
Final 2/20/2025 Not Ready for Inspection NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 2/20/2025 SGSOV Approved NICHOLAS LOPEZ
Smoke Detectors 2/20/2025 Approved NICHOLAS LOPEZ
Final 2/26/2025 OK to Issue CofO NICHOLAS LOPEZ