13909 W LA MAIDA ST 91423
Certificate Information: 13909 W LA MAIDA ST 91423
- Application / Permit
- 24014-10000-01330
- Plan Check / Job No.
- B24LA06019
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Ground Floor Addition and Remodel to an (E) 1-Story SFD
- Permit Issued
- Issued on 7/1/2024
- Issuing Office
- Current Status
- CofO Issued on 8/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2024 | DAVID CASTILLO |
| Corrections Issued | 4/9/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 5/6/2024 | CAROLEAN BASMA |
| Plan Check Approved | 6/13/2024 | CAROLEAN BASMA |
| Issued | 7/1/2024 | APPLICANT |
| CofO in Progress | 8/12/2025 | MISAEL ESPARZA |
| Permit Finaled | 8/28/2025 | RUBEN SALAS |
| CofO Issued | 8/28/2025 | RUBEN SALAS |
| Permit Finaled | 8/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/14/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 5/14/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/19/2024 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 9/6/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/6/2024 | Partial Inspection | MISAEL ESPARZA |
| Piling/Pier/Caisson | 9/6/2024 | Partial Inspection | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 9/13/2024 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 9/18/2024 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/18/2024 | Partial Inspection | MISAEL ESPARZA |
| Piling/Pier/Caisson | 9/18/2024 | Partial Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/26/2024 | Partial Approval | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 10/22/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 10/25/2024 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 11/13/2024 | Corrections Issued | MISAEL ESPARZA |
| Wood Frame | 11/13/2024 | Corrections Issued | MISAEL ESPARZA |
| Gas Test | 11/15/2024 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 11/15/2024 | Partial Approval | MISAEL ESPARZA |
| Wood Frame | 11/15/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2024 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2025 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 1/15/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2025 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Rough | 3/7/2025 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 3/7/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 3/7/2025 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/20/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 3/20/2025 | Approved | MISAEL ESPARZA |
| Green Building Rough | 3/20/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/20/2025 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 3/20/2025 | Approved | MISAEL ESPARZA |
| Shower Pan | 3/20/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/30/2025 | Approved | MISAEL ESPARZA |
| Insulation | 4/30/2025 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 5/8/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/16/2025 | Approved | MISAEL ESPARZA |
| Service/Power Release | 7/8/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Final | 7/17/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 7/17/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 7/22/2025 | Corrections Issued | JACK KARGODORIAN |
| PLUMBING-Final | 7/22/2025 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Final | 7/24/2025 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Final | 7/24/2025 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Final | 8/4/2025 | Approved | MISAEL ESPARZA |
| Final | 8/11/2025 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 8/11/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/11/2025 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 8/11/2025 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 8/11/2025 | Approved | MISAEL ESPARZA |