668 S ALAMEDA ST 90021
Certificate Information: 668 S ALAMEDA ST 90021
- Application / Permit
- 24014-10000-01322
- Plan Check / Job No.
- B24LA05947
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (4) Art Gallery
- Work Description
- (N) 1-STORY BUILDING TO BE USED AS AN ART DISPLAY ZONE
- Permit Issued
- Issued on 6/24/2024
- Issuing Office
- Current Status
- Issued on 6/24/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2024 | HERNAN ARREOLA |
| Assigned to Zoning Architect | 4/4/2024 | CALEB WONG |
| Corrections Issued | 4/8/2024 | HERNAN ARREOLA |
| Quality Review Completed | 4/8/2024 | PETER KIM |
| Plan Check Approved | 6/24/2024 | HERNAN ARREOLA |
| Issued | 6/24/2024 | APPLICANT |
Permit Application Clearance Information
| Green Code | Cleared | 4/25/2024 | AARON COSTA |
| DAS Clearance | Cleared | 5/6/2024 | Sergio Muniz |
| Miscellaneous | Cleared | 5/7/2024 | DAVID URITA |
| Miscellaneous | Cleared | 5/7/2024 | DAVID URITA |
| Miscellaneous | Cleared | 5/7/2024 | DAVID URITA |
| "Q" conditions | Cleared | 5/31/2024 | RUBEN VASQUEZ |
| CPC | Cleared | 5/31/2024 | RUBEN VASQUEZ |
| ZI | Cleared | 5/31/2024 | RUBEN VASQUEZ |
| Zoning Plan Check | Cleared | 6/20/2024 | Sergio Muniz |
Contact Information
| Architect | Raabe,, Evan A; Lic. No.: C32671 | 1528 SHADOW LANE FULLERTON, CA 92831 |
| Contractor | Barling Construction Inc; Lic. No.: 1023529-B | , |
Inspector Information
| RONALD JIMENEZ, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| LARRY ARNICK, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEY BUCHANAN, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| ERNESTO CORRAL, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL ESPINOZA, (213) 482-0307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/17/2025 | Not Ready for Inspection | LARRY ARNICK |
| Footing/Foundation/Slab | 7/22/2025 | Approved | LARRY ARNICK |
| Excavation/Setback/Form/Re-Bar | 8/7/2025 | Not Ready for Inspection | LARRY ARNICK |
| Excavation/Setback/Form/Re-Bar | 8/8/2025 | Approved | LARRY ARNICK |
| Reinforced Masonry Frame | 8/11/2025 | Partial Approval | LARRY ARNICK |
| Excavation/Setback/Form/Re-Bar | 10/3/2025 | Partial Approval | LARRY ARNICK |
| Excavation/Setback/Form/Re-Bar | 11/12/2025 | No Access for Inspection | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 11/17/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 11/26/2025 | Not Ready for Inspection | DAVID BURKHEAD |
| Excavation/Setback/Form/Re-Bar | 12/1/2025 | Partial Approval | LARRY ARNICK |
| Light Gage Steel Frame | 1/27/2026 | Approved | LARRY ARNICK |
| Drywall Nailing | 1/30/2026 | Partial Approval | LARRY ARNICK |
| Green Building Rough | 1/30/2026 | Not Ready for Inspection | LARRY ARNICK |