EPLAN: 29'-3" X 16'-10" ADDITION TO (E) SFD, ALL WORK PER WFPP.
Permit Issued
Issued on 5/10/2024
Issuing Office
Current Status
CofO Issued on 3/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/1/2024 APPLICANT
Assigned to Plan Check Engineer 4/4/2024 LUISANGEL VALENZUELA
Corrections Issued 4/5/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 5/1/2024 LUISANGEL VALENZUELA
Plan Check Approved 5/8/2024 LUISANGEL VALENZUELA
Issued 5/10/2024 APPLICANT
CofO in Progress 3/12/2025 ANTHONY EGSON
Permit Finaled 3/14/2025 ANSON MAGLASANG
CofO Issued 3/14/2025 ANSON MAGLASANG
Permit Finaled 3/14/2025 ANSON MAGLASANG

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/16/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 4/25/2024 AMBER CAMPBELL
Sewer availability Cleared 4/25/2024 AMBER CAMPBELL

Contact Information

Contractor Investors Design And Builders Inc; Lic. No.: 1003930-B       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/15/2024 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 5/24/2024 Partial Approval JAMES CHAVEZ
PLUMBING-Rough 5/24/2024 Partial Approval JAMES CHAVEZ
ELECTRICAL-Rough 6/24/2024 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 6/24/2024 Approved JAMES CHAVEZ
HVAC-Rough 6/24/2024 Not Ready for Inspection JAMES CHAVEZ
PLUMBING-Rough 6/24/2024 Approved JAMES CHAVEZ
Wood Frame 6/24/2024 Not Ready for Inspection JAMES CHAVEZ
Shower Pan 6/27/2024 Not Ready for Inspection BEN MOLSTAD
Wood Frame 6/27/2024 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 7/2/2024 Approved JAMES CHAVEZ
HVAC-Rough 7/2/2024 Approved JAMES CHAVEZ
Interior/Exterior Lathing 7/2/2024 Approved JAMES CHAVEZ
Shower Pan 7/2/2024 Approved JAMES CHAVEZ
Insulation 7/3/2024 Approved JAMES CHAVEZ
Interior/Exterior Lathing 7/3/2024 Not Ready for Inspection JAMES CHAVEZ
Drywall Nailing 7/5/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 7/29/2024 Corrections Issued BEN MOLSTAD
Final 7/29/2024 Corrections Issued BEN MOLSTAD
HVAC-Final 7/29/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Final 7/29/2024 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 7/29/2024 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 7/29/2024 Approved BEN MOLSTAD
Final 9/12/2024 Corrections Issued ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 9/12/2024 SGSOV Approved ANSON MAGLASANG
Final 2/25/2025 Corrections Issued ANSON MAGLASANG
Final 3/11/2025 OK to Issue CofO ANTHONY EGSON